Pune/Project record

MahaRERA · the public record

Midway mall

Nagadwadi · Dattatray Genuji Bhor

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

25 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

25 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100017234

Delivery and registration

When is the project declared for completion?

Midway mall is registered with MahaRERA as P52100017234 and the promoter has declared completion for 25 Dec 2024.

25 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100017234
Registered on24 Jul 2018
Promoter-declared completion25 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Midway mall record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Dattatray Genuji Bhor is the promoter of record on 110 projects registered with MahaRERA, 30 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

110projects

registered with MahaRERA

30flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Midway mall in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
Midway mall1G+125 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Nagadwadi, Pune nashik national Highway, Junnar, Pune, 412412. Per the filed land record, the plot is bounded to the north by Pune Nashik National Highway, to the south by Plot no 294 part, to the east by Plot no 289 and to the west by Plot no 291 and 290. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vadgaon Anand

Mauli Residency
Past its declared completion date · declared completion Dec 2023 · Mauli Infra

Other RERA-registered projects in Pune

Mihir Amara Building - A4
possession by Dec 2026 · Mihir Synthetics
Mihir Amara Phase 1
possession by Dec 2026 · Mihir Synthetics
Mihir Amara Phase II
possession by Dec 2026 · Mihir Homes Realty
Millefiori
possession by Jun 2030 · Futuristic Homes
Millennium Amara
possession by Mar 2028 · Millennium Developers
Millennium Amara Phase 2
possession by Dec 2029 · Millennium Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026