MahaRERA Property Intelligence · Pune

MSR OLIVE

P52100008615 · Ambegaon · promoter Mind Space Realty

Certificate SignedDue 31 Mar 2025

Delivery & Registration

MahaRERA registrationP52100008615
Registered on19 Aug 2017
Promoter-declared completion31 Mar 2025
Current statusCertificate Signed
Against todayabout 16 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
Wing E1G+930 Jun 2021
Wing G1G+930 Jun 2021
Wing F1G+330 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Senior Division11172014Consent Term Filed And Dispute Resolved

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202331 Mar 2023The current registration has validity of project completion is till June 2021. Due to the current Pandemic situation and unavoidable reasons we the developer/s are not able to comp
30 Jun 202131 Mar 2025Mind Space Realty Pvt Ltd has successfully completed the residential project MSR OLIVE, and possession has been handed over to all of the allottees. Under the project MSR OLIVE, wi

Location, Land & Connectivity

Located at Ambegaon, Ambegaon BK, Pune City, Pune, 411046. Per the filed land record, the plot is bounded to the north by S No 47-1 47-5 43, to the south by S No 47-7, to the east by S No 44 and to the west by S No 47-3. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Junction / city centre9 km
Magarpatta / Hadapsar IT11 km
Baner–Balewadi belt14 km
Kharadi / EON IT Park15 km
Pune Int'l Airport (Lohegaon)17 km
Hinjewadi Rajiv Gandhi IT Park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mind Space Realty Pvt. Ltd. is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Mind Space Realty Pvt. Ltd.

Mind Space Realty Pvt. Ltd.
FlaggedPune
Mind Space Realty Pvt. Ltd.
FlaggedPune

Other RERA-registered projects in Katraj

Aishwarya Heights
possession by Jul 2026 · Shree Sadguru Construction
Basil Chandrakant
possession by Jul 2026 · Shree Sadguru Developers
Vastushree Phase-1
possession by Aug 2026 · Vastu Construction
Capella
possession by Aug 2026 · D K Realties
Divya Elite
possession by Aug 2026 · RRS Infracon LLP
Yogamrut
Not filing quarterly progress reports · possession by Aug 2026 · Jay Ganesh Buildcon

Major developers building in Katraj

Other RERA-registered projects in Pune

MSR Regency
declared completion Dec 2018 · Bhandari Infrastructure & Constructi
MSR Seasons
declared completion Dec 2025 · Mind Space Realty Pvt. Ltd.
MSR Square
declared completion Dec 2018 · Mind Space Realty Pvt. Ltd.
MST Aspire
declared completion May 2025 · MST Group
Mtriumph
declared completion Mar 2024 · Kingsville Reality LLP
Mudra
declared completion Dec 2022 · Classic Promoters And Builders Private L

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026