MahaRERA Property Intelligence · Pune

MSR REGENCY

P52100004593 · promoter Bhandari Infrastructure Construction

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP52100004593
Registered on09 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Bhandari Infrastructure Construction is the promoter of record on 42 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
MSR REGENCY1G+831 Jul 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201831 Jul 2019Completion certificate is to be received from the competent authority

Location, Land & Connectivity

Located at Pune City, Pune, 411001. Per the filed land record, the plot is bounded to the north by 9M WIDE ROAD, to the south by CTS NO 830, to the east by CTS NO 846 and to the west by CTS NO 844. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre2 km
Magarpatta / Hadapsar IT6 km
Kharadi / EON IT Park9 km
Pune Int'l Airport (Lohegaon)9 km
Baner–Balewadi belt11 km
Hinjewadi Rajiv Gandhi IT Park17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Bhandari Infrastructure & Construction Development Pvt. Ltd. is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Bhandari Infrastructure & Construction De

Bhandari Infrastructure & Construction Development Pvt. Ltd.
FlaggedPune

Other RERA-registered projects in Ghorpadi

IVY BY Vistaara Homes
possession by Jul 2026 · Vistaarahomes Realty LLP
Profitbay - BT Kawade Road
possession by Aug 2026 · Venturespro Projects LLP
Royal Glen
possession by Sep 2026 · Stargaze Buildcon
Ganga Bhagyoday E Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Ganga Bhagyoday F Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Ganga Bhagyoday Tower
possession by Dec 2026 · Legends County Landmark Pvt Ltd

Major developers building in Ghorpadi

Other RERA-registered projects in Pune

MSR Seasons
declared completion Dec 2025 · Mind Space Realty Pvt. Ltd.
MSR Square
declared completion Dec 2018 · Mind Space Realty Pvt. Ltd.
MST Aspire
declared completion May 2025 · MST Group
Mtriumph
declared completion Mar 2024 · Kingsville Reality LLP
Mudra
declared completion Dec 2022 · Classic Promoters And Builders Private L
Mudra Heights
declared completion Oct 2022 · JAI Ganesh Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026