Pune/Project record

MahaRERA · the public record

GAGAN UNO

Sangamwadi · GAGAN ACE DEVLOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

20units filed as unsoldInventory · 12 September 2026
30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
67registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100001400

Delivery and registration

When is the project declared for completion?

GAGAN UNO is registered with MahaRERA as P52100001400 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100001400
Registered on28 Jul 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GAGAN UNO record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Gagan Ace Devlopers is the promoter of record on 74 projects registered with MahaRERA, 15 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

74projects

registered with MahaRERA

15flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In GAGAN UNO, 47 of 67 homes filed with MahaRERA are recorded as sold or booked, about 70%, and 20 remain available.

70%sold

47 of 67 homes

₹139.76 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹109.43 Cr (about 78%) is recorded as collected and ₹18.70 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 47 registered agreements, the effective carpet rate is ₹23,290/sqft, with eight in ten falling between ₹15,308 and ₹277,290 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 4402425 sqft (39.49 sqm)₹91.84 Lakh
Floor 4403291 sqft (27.06 sqm)₹54.18 Lakh
Floor 4404296 sqft (27.51 sqm)₹56.09 Lakh
Floor 4408/409796 sqft (73.92 sqm)₹12.74 Lakh
Floor 7701476 sqft (44.18 sqm)₹70.74 Lakh
Floor 7702423 sqft (39.29 sqm)₹81.38 Lakh
Floor 7703868 sqft (80.66 sqm)₹1.64 Cr
Floor 7704371 sqft (34.49 sqm)₹7.91 Cr
Floor 7705443 sqft (41.14 sqm)₹74.16 Lakh
Floor 7706568 sqft (52.79 sqm)₹1.06 Cr
Floor 7707417 sqft (38.7 sqm)₹81.38 Lakh
Floor 7708693 sqft (64.4 sqm)₹1.24 Cr
Floor 8801476 sqft (44.18 sqm)₹70.74 Lakh
Floor 8802423 sqft (39.29 sqm)₹81.38 Lakh
Floor 8803868 sqft (80.66 sqm)₹1.64 Cr
Floor 8804371 sqft (34.49 sqm)₹1.64 Cr
Floor 8805443 sqft (41.14 sqm)₹74.16 Lakh
Floor 8806568 sqft (52.79 sqm)₹1.06 Cr
Floor 8807417 sqft (38.7 sqm)₹81.38 Lakh
Floor 8808693 sqft (64.4 sqm)₹1.24 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 47 homes carry one, and 20 of the 67 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
408/409796 sqftRs 1.1810 cr typical, over Rs 1.0639 cr to Rs 1.2180 cr3 filed on this stack, floors 3–6

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In GAGAN UNO, 18 of the 20 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 19 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14 and 67 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
GAGAN UNO1G+146731 Dec 2019

Unit mix on the filing: 67 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020Reason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other

Location, Land & Connectivity

Located at Sangamwadi, Dhole patil road, Pune City, Pune, 411001. Per the filed land record, the plot is bounded to the north by RESIDENTIAL BUILDING, to the south by RESIDENTIAL BUILDING, to the east by 24M MUNCIPAL ROAD and to the west by 6M INTERNAL ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre1 km
Magarpatta / Hadapsar IT6 km
Kharadi / EON IT Park7 km
Pune Int'l Airport (Lohegaon)7 km
Baner–Balewadi belt11 km
Hinjewadi Rajiv Gandhi IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghorpadi

Royal Glen
possession by Sep 2026 · Stargaze Buildcon
Ganga Bhagyoday E Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Ganga Bhagyoday F Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Boulevard Tower A2
possession by Dec 2026 · Bramhacorp Limited
Casaverde
possession by Dec 2026 · Skyboat Infrastructure Unit 1 LLP
Eternia Phase 2
possession by Dec 2026 · Venturespro Projects LLP

Major developers building in Ghorpadi

Other RERA-registered projects in Pune

Gaikwad Florio
possession by Dec 2029 · Gaikwad Developers
Gaikwad Nirvanas
declared completion Mar 2026 · Gaikwad Developers
Gaikwad Unico
possession by Nov 2028 · Gaikwad Realty
Gajanan Hights
declared completion Aug 2022 · Classic Construction
Gajanan Prasad
possession by Mar 2027 · Hari OM Ventures
Gajara Pacific
declared completion Mar 2026 · Riddhi Infra

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026