Pune/Project record

MahaRERA · the public record

Gagan Commerce Centre

Sangamwadi, Pune · Gagan I-Land Township Private limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100016445

Delivery and registration

When is the project declared for completion?

Gagan Commerce Centre is registered with MahaRERA as P52100016445 and the promoter has declared completion for 30 Mar 2024.

30 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100016445
Registered on11 May 2018
Promoter-declared completion30 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Gagan Commerce Centre record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Gagan I-Land Township is the promoter of record on 117 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

117projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Gagan Commerce Centre in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
GCC Tower Floor 1-41G+1031 Mar 2023
GCC Tower Proposed Floor 5-171-31 Mar 2023
GCC Tower Proposed Floor 181-30 Nov 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Sangamwadi, Pune, CTS NO 23, Plot no 262/B, 262/C, Pune City, Pune, 411001. Per the filed land record, the plot is bounded to the north by F P No 262P CTS no 23P, to the south by 30 Metre wide DP Road, to the east by 30 metre wide DP Road and to the west by F P No 261. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre1 km
Magarpatta / Hadapsar IT5 km
Pune Int'l Airport (Lohegaon)6 km
Kharadi / EON IT Park6 km
Baner–Balewadi belt11 km
Hinjewadi Rajiv Gandhi IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghorpadi

Royal Glen
possession by Sep 2026 · Stargaze Buildcon
Ganga Bhagyoday E Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Ganga Bhagyoday F Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Boulevard Tower A2
possession by Dec 2026 · Bramhacorp Limited
Casaverde
possession by Dec 2026 · Skyboat Infrastructure Unit 1 LLP
Eternia Phase 2
possession by Dec 2026 · Venturespro Projects LLP

Major developers building in Ghorpadi

Other RERA-registered projects in Pune

Gagan Ela
declared completion Jun 2025 · Gagan Landmarks LLP
Gagan Kapital
declared completion Dec 2021 · Gagan ACE Developers
Gagan Klara
declared completion Mar 2026 · Gagan Housing And Landmarks LLP
Gagan Lawish Phase 2
declared completion Dec 2020 · Gagan ACE Infra
Gagan Meher
declared completion Dec 2024 · Gagan Galaxy Realty LLP
Gagan Myra
possession by Jun 2029 · Gagan Galaxy Realty LLP

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026