MahaRERA Property Intelligence · Pune

Gagan Klara

P52100019739 · Balewadi · promoter Gagan Housing And

Certificate SignedDue 30 Mar 2026

Delivery & Registration

MahaRERA registrationP52100019739
Registered on05 Mar 2019
Promoter-declared completion30 Mar 2026
Current statusCertificate Signed
Against todayabout 4 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~95.8% of the estimated project cost incurred as of the last certificate (₹96.16 Cr spent against a ₹100.38 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 373 homes filed with MahaRERA, 308 are sold/booked (303 with registered agreements + 5 booked) and 65 remain available (~83% sold) — selling steadily. Buyers have committed ₹221.59 Cr in agreement value so far. Of that, ₹198.97 Cr (~90%) is already collected, ₹22.61 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 308 registered agreements, the effective carpet rate is ₹10,777/sqft (typical range ₹9,119–₹13,792) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24 and 373 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building D - Commercial And MHADA1G+13121-
Wing A1G+2484-
Wing B1G+2484-
Wing C1G+2484-

Unit mix on the filing: 340 residential and 33 non-residential (shops/offices).

Complaints & Orders

33 complaints are on the MahaRERA record for this project, with orders passed in 5. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1250068726/02/2025Gauri Vasant Vazarkar vs Gagan Housing And Landmarks LLPorder passed
CC1250073604/03/2025Hitesh Srichand Jairamdasani vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250091916/03/2025Sandeep Ashok Kinkar vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250118209/04/2025Tushar Deepak Thorat vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250118309/04/2025Tejas Deepak Thorat vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250118509/04/2025Akshay Chandrakant Tambade vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250145229/04/2025Pravin Balaji Dhayfule vs Gagan Housing And Landmarks LLPorder passed
CC1250154710/05/2025Chetan Sunilkumar Jain vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250154610/05/2025Sumeet Dinkar Gosavi vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250156012/05/2025Satish Dhirubhai Mavani vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250159514/05/2025Alok Narayan vs Gagan Housing And Landmarks LLPorder passed
CC1250159715/05/2025AMRUT ANIL SABNIS vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250161818/05/2025Sanket Patil vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250200819/06/2025Atul Achyut Jadhav vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250200919/06/2025Pavan Diwakar Bonkinpillewar vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250211727/06/2025Vaibhav Hemraj Chhaparghare vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250225005/07/2025ANUP ASHOK PATTIWAR vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250224905/07/2025Dnyaneshwar Digambar Gorade vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250224705/07/2025ABHAY Om PRAKASH vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250248219/07/2025Priyanka Pramod Ghare vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250248119/07/2025Hemlata Saish Chavali vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250248319/07/2025Rahul Kailas Shinde vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250261229/07/2025Santosh Hari Lokhande vs Gagan Housing And Landmarks LLPorder passed
CC1250283113/08/2025Tanushree Jaysingh Shinde vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250291619/08/2025Ankit Patil vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250335219/09/2025AARATRIKA SEN vs Gagan Housing And Landmarks LLPorder passed
CC1250335319/09/2025NILESH SHANKAR KHATTI vs Gagan Housing And Landmarks LLPpending / no order on file
CC1250376728/10/2025Vikar Ansar Sheikh vs Gagan Housing And Landmarks LLPpending / no order on file
CC1260051029/01/2026MAYUR NAMDEO BALWAKAR Q vs Gagan Housing And Landmarks LLPpending / no order on file
CC1260058202/02/2026Rajesh Shankarrao Padgilwar vs Gagan Housing And Landmarks LLPpending / no order on file
CC1260305323/05/2026Sakharam Kisan Shinde vs Gagan Housing And Landmarks LLPpending / no order on file
CC1260344204/06/2026Sheetal Wattamwar vs Gagan Housing And Landmarks LLPpending / no order on file
CC1260429409/07/2026Satish Suryakant Nimje vs Gagan Housing And Landmarks LLPpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202430 Mar 20251) We are the Promoters of the Real Estate Project known as “GAGAN KLARA” under implementation by us on land admeasuring 00 H 89 Ares bearing Survey Nos. 38 Hissa No. 8A situate, l
30 Mar 202430 Mar 2026We have received the part occupancy certificate bearing no. OCC/0589/24 on dated 21/08/2024 for building D. And we are in process of obtaining all NOC’s required for application of

Location, Land & Connectivity

Located at Balewadi, Hi Street, Haveli, Pune, 411045. Per the filed land record, the plot is bounded to the north by Survey No 38 Hissa No 7, to the south by Survey No 38 Hissa No 8 Part and 9, to the east by Road and to the west by Survey No 38 Hissa No 5. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Baner

7 Business BAY
possession by Jul 2026 · Saaj Buildcon Private Limited
Maitreya
Not filing quarterly progress reports · possession by Jul 2026 · Vaibhav Shamrao Taro
Mercury
possession by Aug 2026 · SB Real Estate Private Limited
Aarambh
possession by Aug 2026 · ADI Realtors
Nancy Hillview A-1
possession by Aug 2026 · M/S Sarsan Aawishkar Properties
Truspace Platina
possession by Aug 2026 · Atharva Developments

Major developers building in Baner

Other RERA-registered projects in Pune

Gagan Lawish Phase 2
declared completion Dec 2020 · Gagan ACE Infra
Gagan Meher
declared completion Dec 2024 · Gagan Galaxy Realty LLP
Gagan Myra
possession by Jun 2029 · Gagan Galaxy Realty LLP
Gagan Nulife Phase 1
declared completion Mar 2018 · Gagan Lifespace
Gagan Nulife Phase 2
declared completion Sep 2022 · Gagan Lifespace
Gagan Nulife Phase 3
declared completion Oct 2025 · Gagan Lifespace

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026