Pune/Project record

MahaRERA · the public record

GAGAN NULIFE PHASE 3

Kamshet · GAGAN LIFESPACE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Oct 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Oct 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100024677

Delivery and registration

When is the project declared for completion?

GAGAN NULIFE PHASE 3 is registered with MahaRERA as P52100024677 and the promoter has declared completion for 01 Oct 2025.

01 Oct 2025

declared completion

11months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100024677
Registered on28 Feb 2020
Promoter-declared completion01 Oct 2025
Current statusCertificate Signed
Against todayabout 11 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GAGAN NULIFE PHASE 3 record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GAGAN NULIFE PHASE 3 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Building B1G+1401 Oct 2024

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for GAGAN NULIFE PHASE 3, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000031050929/02/2024Jaywant Mungekar vs Gagan realtors though its partner Sushil Agarwal and othersorder passed

Location, Land & Connectivity

Located at Kamshet, Pune Mumbai Old Highway, Pune City, Pune, 410405. Per the filed land record, the plot is bounded to the north by 12m Internal Road, to the south by Open Space, to the east by 12m Internal Road and to the west by A BUILDING. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park26 km
Baner–Balewadi belt32 km
Pune Junction / city centre42 km
Pune Int'l Airport (Lohegaon)43 km
Kharadi / EON IT Park46 km
Magarpatta / Hadapsar IT47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Gagan Lifespace is the promoter on 5 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Gagan Lifespace

Gagan Lifespace
Not filing quarterly progress reportsPune
Gagan Lifespace
Past its declared completion datePune

Other RERA-registered projects in Kamshet

Aranya
possession by Dec 2026 · Karmaa Builders
Forisaqua - Phase 2
possession by Dec 2026 · Vijay Kumar Ratanchand Javeri
Stellar 8
possession by Dec 2026 · Iraah Lifespaces LLP
Antaaya Villas
possession by Dec 2027 · Antaaya Builders LLP
Palaash Valley
possession by Dec 2027 · Good Will Developper
Divine Wonders
possession by Dec 2028 · M/S Zircon Properties

Major developers building in Kamshet

Other RERA-registered projects in Pune

Gagan Nulife Phase 4
declared completion Oct 2025 · Gagan Lifespace
Gagan Nulife Phase 5
declared completion Apr 2024 · Gagan Lifespace
Gagan Panama Phase 1
declared completion Nov 2022 · Gagan Panama Buildscapes LLP
Gagan Signet
declared completion Nov 2022 · Gagan Realtors LLP
Gagan Southcode
declared completion Mar 2024 · Gagan ACE Developers
Gagan Tisha
declared completion Oct 2022 · Gagan Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026