MahaRERA Property Intelligence · Pune

GAGAN NULIFE PHASE 3

P52100024677 · Kamshet · promoter Gagan Lifespace

Certificate SignedDue 01 Oct 2025

Delivery & Registration

MahaRERA registrationP52100024677
Registered on28 Feb 2020
Promoter-declared completion01 Oct 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Building B1G+1401 Oct 2024

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000031050929/02/2024Jaywant Mungekar vs Gagan realtors though its partner Sushil Agarwal and othersorder passed

Location, Land & Connectivity

Located at Kamshet, Pune Mumbai Old Highway, Pune City, Pune, 410405. Per the filed land record, the plot is bounded to the north by 12m Internal Road, to the south by Open Space, to the east by 12m Internal Road and to the west by A BUILDING. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park26 km
Baner–Balewadi belt32 km
Pune Junction / city centre42 km
Pune Int'l Airport (Lohegaon)43 km
Kharadi / EON IT Park46 km
Magarpatta / Hadapsar IT47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Gagan Lifespace is the promoter on 5 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Gagan Lifespace

Gagan Lifespace
Not filing quarterly progress reportsPune
Gagan Lifespace
Past its declared completion datePune

Other RERA-registered projects in Kamshet

Peninsula Centre Commercial Building Shopping Complex
possession by Jul 2026 · Peninsula Land Limited
Aranya
possession by Dec 2026 · Karmaa Builders
Forisaqua - Phase 2
possession by Dec 2026 · Vijay Kumar Ratanchand Javeri
Stellar 8
possession by Dec 2026 · Iraah Lifespaces LLP
Antaaya Villas
possession by Dec 2027 · Antaaya Builders LLP
Palaash Valley
possession by Dec 2027 · Good Will Developper

Major developers building in Kamshet

Other RERA-registered projects in Pune

Gagan Nulife Phase 4
declared completion Oct 2025 · Gagan Lifespace
Gagan Nulife Phase 5
declared completion Apr 2024 · Gagan Lifespace
Gagan Panama Phase 1
declared completion Nov 2022 · Gagan Panama Buildscapes LLP
Gagan Signet
declared completion Nov 2022 · Gagan Realtors LLP
Gagan Southcode
declared completion Mar 2024 · Gagan ACE Developers
Gagan Tisha
declared completion Oct 2022 · Gagan Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026