31 Jul 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100017555

Delivery and registration

When is the project declared for completion?

NATEKAR COMPLEX is registered with MahaRERA as P52100017555 and the promoter has declared completion for 31 Jul 2024.

31 Jul 2024

declared completion

26months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100017555
Registered on28 Aug 2018
Promoter-declared completion31 Jul 2024
Current statusCertificate Signed
Against todayabout 26 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NATEKAR COMPLEX record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NATEKAR COMPLEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
A BUILDING1G+531 Jul 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BHOSARI, BHOSARI, Haveli, Pune, 411026. Per the filed land record, the plot is bounded to the north by OPEN SPACE, to the south by 18 MTR WIDE ROAD, to the east by 9 MTR WIDE ROAD AND PLOT NO 71 TO 75 and to the west by NALLA. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhosari

Ellora Shopee
possession by Sep 2026 · Ellora Realities Private Limited
Atlantis
possession by Dec 2027 · Atharva Buildwell
Vision Ekaan
possession by Dec 2027 · Vision Creative Spaces
Santiago Skyworld
possession by Jun 2028 · Santiago Realtech
TEN BKC
possession by Dec 2029 · Mahalaxmi Land Developers
Shrikisan Enclave
declared completion Jul 2026 · M/s. Tirupathi Properties Through Prop M

Other RERA-registered projects in Pune

Natraj Residency
possession by Dec 2027 · Vikram Vedprakash Agarwal
Natraj Vatsa
declared completion Mar 2024 · Natraj Realtors
Nature Castle
possession by Jun 2029 · Shah And Shah Realty
Nature Nest
declared completion Dec 2024 · Prithvi Pinnacle Associates
Nature Nest
possession by Mar 2028 · Roots Reality
Nature Park
declared completion Sep 2020 · SAI Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.