Pune/Project record

MahaRERA · the public record

NAVJYOT ABHA PHASE I

Pune · SUMERU BUILDCON PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100011535

Delivery and registration

When is the project declared for completion?

NAVJYOT ABHA PHASE I is registered with MahaRERA as P52100011535 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100011535
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NAVJYOT ABHA PHASE I record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sumeru Buildcon is the promoter of record on 11 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

11projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NAVJYOT ABHA PHASE I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
C1G+13-
D1G+13-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for NAVJYOT ABHA PHASE I, with orders passed in 0 of them.

2complaints

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1240044317/10/2024Jaydeep padmakar pathakji vs SUMERU BUILDCON PRIVATE LIMITEDpending / no order on file
CC1250383701/11/2025Subramanyam Vilas Ghante vs SUMERU BUILDCON PRIVATE LIMITEDpending / no order on file

Location, Land & Connectivity

Located at Haveli, Pune, 411041. Per the filed land record, the plot is bounded to the north by SURVEY NO 149, to the south by PROPERTYOF VAISHNAVI PROMOTERS AND BUILDERS, to the east by REMAINING PART OF S NO 150-1 AND S NO 150-3 and to the west by REMAINING PLOT ARE AT SURVEY NO 150-1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~117 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park117 km
Baner–Balewadi belt123 km
Pune Junction / city centre133 km
Pune Int'l Airport (Lohegaon)134 km
Kharadi / EON IT Park137 km
Magarpatta / Hadapsar IT138 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sumeru Buildcon Private Limited is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Sumeru Buildcon Private Limited

Sumeru Buildcon Private Limited
Not filing quarterly progress reportsPune

Other RERA-registered projects in Dhayari

Aqura Pride
possession by Sep 2026 · Aqura Builder And Developer Private Limi
Majestique Swapnangan Wing A And Wing B
possession by Sep 2026 · Majestique Horizon LLP
Tridal Samruddhi
possession by Sep 2026 · M/s. Tridal Associates
Vasant Vihar A Wing
possession by Sep 2026 · A R Developers
Homedale
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Navjyot Abha Phase II B And D
Not filing quarterly progress reports · possession by Dec 2026 · Sumeru Buildcon Private Limited

Major developers building in Dhayari

Other RERA-registered projects in Pune

Navjyot Abha Phase II B And D
possession by Dec 2026 · Sumeru Buildcon Private Limited
Navkaar Heights
declared completion Dec 2024 · Navkaar NX Developers LLP
Navkar A Building
declared completion Jun 2019 · Majestique Lifespaces LLP
Navkar Anand
declared completion Aug 2025 · Four Pillars
Navkar Park
declared completion Dec 2019 · Parkons Trendz
Navkar Park
declared completion Mar 2023 · Himalaya Landmarks Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026