MahaRERA Property Intelligence · Pune

Nirmiti Royal

P52100006518 · promoter Nirmiti Homes

Certificate SignedDue 30 Sep 2020

Delivery & Registration

MahaRERA registrationP52100006518
Registered on14 Aug 2017
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 70 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Nirmiti Homes is the promoter of record on 76 projects, of which 12 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Nirmiti Royal A1G+8-
Nirmiti Royal B1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202030 Mar 20201. Recovery from customers is not regular 2. Irregular River sand Supply

Location, Land & Connectivity

Located at Baramati, Pune, 413102. Per the filed land record, the plot is bounded to the north by 15 M Road, to the south by Part of Survey No 71, to the east by Part of Survey No 71 and to the west by Part of Survey No 71. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~81 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Magarpatta / Hadapsar IT81 km
Kharadi / EON IT Park82 km
Pune Int'l Airport (Lohegaon)85 km
Pune Junction / city centre86 km
Baner–Balewadi belt97 km
Hinjewadi Rajiv Gandhi IT Park102 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Baramati

Nirvana Elite
possession by Jul 2026 · Akash Jayesh Associates
Sharada Baug
possession by Aug 2026 · Mandar Shrikant Sikachi
G G Capital
possession by Aug 2026 · GG Builders AND Developers
Mayureshwar Icon
possession by Sep 2026 · Mayureshwar Reality AND Developers
Gadhavenanaware Heights
possession by Sep 2026 · Shri Developers
Shivshri Heights
possession by Sep 2026 · Shivashri Buildcon

Major developers building in Baramati

Other RERA-registered projects in Pune

Nirmiti Vasundhara Park
declared completion Dec 2018 · Vasundhara Nirmiti Homes
Nirmiti Vihar
declared completion Aug 2018 · Nirmiti Associates
Nirmiti Vihar
possession by Dec 2031 · Nirmiti Associates
Nirvana
declared completion Jun 2022 · Arnav Builders
Nirvana
possession by Dec 2026 · Nirman Skylines LLP
Nirvana Beyond A Wing
declared completion Jun 2021 · Diamond Nexus Properties

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026