22 Jul 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

22 Jul 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013565

Delivery and registration

When is the project declared for completion?

NIRVANA HOMES is registered with MahaRERA as P52100013565 and the promoter has declared completion for 22 Jul 2022.

22 Jul 2022

declared completion

50months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013565
Registered on13 Oct 2017
Promoter-declared completion22 Jul 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NIRVANA HOMES record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Fortune Elite is the promoter of record on 122 projects registered with MahaRERA, 15 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

122projects

registered with MahaRERA

15flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NIRVANA HOMES in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
NIRVANA HOMES1G+120 Apr 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered20 Oct 2021Due to lockdown on account of Covid-19 pandemic, availability of workers became issue and still it is not fully resolved as Pune has become the hub for CORONA with highest no of in
20 Oct 202122 Jul 2022Increase in Floor Space Index (FSI) Area.

Location, Land & Connectivity

Located at Pimpri, Pune, Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by 7 AND HALF METER WIDE ROAD, to the south by 7 AND HALF METER WIDE ROAD, to the east by SERVEY NO 94P and to the west by SERVEY NO 78. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park9 km
Baner–Balewadi belt14 km
Pune Junction / city centre22 km
Pune Int'l Airport (Lohegaon)22 km
Kharadi / EON IT Park26 km
Magarpatta / Hadapsar IT27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ravet

City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited
Madhuban
possession by Sep 2026 · Godrej Skyline Developers Limited
OM Mangalam Chaitanya
possession by Sep 2026 · Shri Associates
OM Mangalam Disha
possession by Sep 2026 · Shri Associates

Major developers building in Ravet

Other RERA-registered projects in Pune

Nirvana Homes
possession by Dec 2028 · Not Available
Nirvana Lakeview Retreat
possession by Mar 2028 · Nirvana Creators AND Developers
Nirvana Life County
declared completion Mar 2025 · Khandve Nirvana Realty
Nirvana Mansarovar
possession by Nov 2028 · Nirvana Creators
Nirvighna Pride
possession by Dec 2028 · Nilesh Bapusaheb Kakade
Nisarg Ansh
possession by Dec 2026 · Ganesh Vasant Walke

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026