Pune/Project record

MahaRERA · the public record

LITTLE EARTH MASULKAR CITY PHASE 3

KIWALE · Kolte-Patil Developers Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014875

Delivery and registration

When is the project declared for completion?

LITTLE EARTH MASULKAR CITY PHASE 3 is registered with MahaRERA as P52100014875 and the promoter has declared completion for 30 Jun 2020.

30 Jun 2020

declared completion

75months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014875
Registered on09 Jan 2018
Promoter-declared completion30 Jun 2020
Current statusCertificate Signed
Against todayabout 75 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LITTLE EARTH MASULKAR CITY PHASE 3 record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Kolte-Patil is the promoter of record on 91 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

91projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for LITTLE EARTH MASULKAR CITY PHASE 3 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
C151G+1730 Jun 2020
C171G+1729 Jun 2020
C181G+1730 Jun 2020
A COMM1G+230 Jun 2020

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for LITTLE EARTH MASULKAR CITY PHASE 3, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000002293608/06/2019RAJANISHH CHOPRAA vs 1) Sampada Realities Pvt. Ltd.,order passed
CC00500000002341011/09/2020BHAGYESH BALASO PATIL vs Sampada Realities Private Limitedorder passed
CC00500000017787815/12/2022Shrenik Vijay Setiya vs Sampada Realities Pvt Ltdorder passed
CC00500000017787429/11/2022Harshal Vinod Bafna vs Sampada Realities Pvt Ltdorder passed
CC00500000017791015/12/2022Meena Vijay Setiya vs Sampada Realities Pvt Ltdorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 2021Due to unfavourable current market conditions, slow demand for the said project, adverse performance by the principle contractor and ban on subvention scheme it has impacted the pr
29 Jun 202128 Jun 2023Due to Pandemic of Covid-19, project completion milestones were delayed due to non-availability of labour and material procurement issues. Also mainly the principal contractor did
28 Jun 202331 Dec 2023as mentioned in application

Location, Land & Connectivity

Located at KIWALE, KIWALE MAMURDI ROAD, Pune City, Pune, 412101. Per the filed land record, the plot is bounded to the north by PROPOSED D P ROAD, to the south by BY SR NO 19 REMAINING LAND, to the east by BY PROPOSED ROAD SR NO 20 and to the west by BY ROAD MAMURDI VILLAGE FRONTIER. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park9 km
Baner–Balewadi belt13 km
Pune Junction / city centre22 km
Pune Int'l Airport (Lohegaon)23 km
Kharadi / EON IT Park27 km
Magarpatta / Hadapsar IT28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kolte-Patil Developers Limited is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Kolte-Patil Developers Limited project & its RERA track record →

Other flagged projects by Kolte-Patil Developers Limited

Kolte-Patil Developers Limited
FlaggedPune
Kolte-Patil Developers Limited
FlaggedPune
Kolte-Patil Developers Limited
FlaggedPune
Kolte-Patil Developers Limited
FlaggedPune

Other RERA-registered projects in Ravet

City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited
Madhuban
possession by Sep 2026 · Godrej Skyline Developers Limited
OM Mangalam Chaitanya
possession by Sep 2026 · Shri Associates
OM Mangalam Disha
possession by Sep 2026 · Shri Associates

Major developers building in Ravet

Other RERA-registered projects in Pune

Little Nest
declared completion Dec 2025 · Arma APC Housingllp
Livience Aleenta
possession by Dec 2028 · Livience Lifespace Private Limited
Livience Aleenta- Phase II
possession by May 2028 · Livience Lifespace Private Limited
Livience Aleenta Phase III
possession by Dec 2030 · Livience Lifespace Private Limited
Livience Unione
possession by Dec 2030 · Livience Lifespace Private Limited
Living Fantasy
declared completion Sep 2018 · Living Cities Pvt. Ltd.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026