MahaRERA Property Intelligence · Pune

FOREST GROVE AT GODREJ PARK GREENS

P52100023129 · MAMURDI VILLAGE · promoter Godrej Properties

Certificate SignedDue 30 Sep 2027

Delivery & Registration

MahaRERA registrationP52100023129
Registered on02 Dec 2019
Promoter-declared completion30 Sep 2027
Current statusCertificate Signed
Against today14 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Godrej Properties is the promoter of record on 109 projects, of which 8 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~70.7% of the estimated project cost incurred as of the last certificate (₹264 spent against a ₹373 estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 1139 homes filed with MahaRERA, 1133 are sold/booked (1079 with registered agreements + 54 booked) and 6 remain available (~99% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹566.53 Cr in agreement value so far. Of that, ₹373.77 Cr (~66%) is already collected, ₹192.76 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 1133 registered agreements, the effective carpet rate is ₹9,106/sqft (typical range ₹7,900–₹10,251) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1GFGA50106517 sqft (48.03 sqm)₹26.44 Lakh
Floor 16GFGA41605512 sqft (47.53 sqm)₹26.17 Lakh
Floor 17GFGA11704633 sqft (58.83 sqm)₹32.39 Lakh
Floor 21GFGA62103517 sqft (48.03 sqm)₹26.44 Lakh
Floor 21GFGA62104633 sqft (58.83 sqm)₹32.39 Lakh
Floor 22GFGA32201632 sqft (58.74 sqm)₹32.34 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22 and 1139 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
TOWER A11G+20154-
TOWER A21G+17132-
TOWER A41G+22170-
TOWER A51G+22170-
TOWER A61G+22170-
TOWER A71G+22170-
TOWER A31G+22173-

Unit mix on the filing: 1139 residential.

Complaints & Orders

34 complaints are on the MahaRERA record for this project, with orders passed in 5. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000006448508/08/2020ASHOK BABAJI SABLE vs GODREJ SKYLINE DEVELOPERS PVT LTDorder passed
CC00500000007520411/02/2021DEVENDRA NATH TRIPATHI & DEESHA GORASIA vs GODREJ SKYLINE DEVELOPERS PRIVATE LTDorder passed
CC1250045711/02/2025ASHISH SHRIVASTAVA vs GODREJ SKYLINE DEVELOPERS PRIVATE LIMITEDpending / no order on file
CC1250054517/02/2025Dilip Sardesai vs GODREJ SKYLINE DEVELOPERS PRIVATE LIMITEDpending / no order on file
CC1250054917/02/2025Sangam Sardesai vs GODREJ SKYLINE DEVELOPERS PRIVATE LIMITEDpending / no order on file
CC1250158414/05/2025ABHAY KUMAR DHUWE vs GODREJ SKYLINE DEVELOPERS PRIVATE LIMITEDpending / no order on file
CC1250212528/06/2025Jitendra Pathak vs GODREJ SKYLINE DEVELOPERS PRIVATE LIMITEDorder passed
CC1250253323/07/2025Deepankar Dilip Sheet vs Godrej Skyline Developers Limitedorder passed
CC1250428804/12/2025NIHAR SUBRATO BANERJEE vs Godrej Skyline Developers Limitedpending / no order on file
CC1250409220/11/2025Prasad Pralhad Khamkar vs Godrej Skyline Developers Limitedorder passed
CC1250423530/11/2025KAPIL ASHOKRAO GAHUKAR vs Godrej Skyline Developers Limitedpending / no order on file
CC1250466329/12/2025Nihit Pramod Chauhan vs Godrej Skyline Developers Limitedpending / no order on file
CC1260212811/04/2026Vittal Kishan Jakore vs Godrej Skyline Developers Limitedpending / no order on file
CC1260221615/04/2026Sachitanand Chandradeo Singh vs Godrej Skyline Developers Limitedpending / no order on file
CC1260221115/04/2026Pranit Pramod Nikam vs Godrej Skyline Developers Limitedpending / no order on file
CC1260242625/04/2026Ranganath Krishna Bhat vs Godrej Skyline Developers Limitedpending / no order on file
CC1260246327/04/2026Mohit Rajiv Badhe vs Godrej Skyline Developers Limitedpending / no order on file
CC1260292818/05/2026Subodh Anand vs Godrej Skyline Developers Limitedpending / no order on file
CC1260303122/05/2026SUDHIR KADAM vs Godrej Skyline Developers Limitedpending / no order on file
CC1260306223/05/2026Vivek Digwani vs Godrej Skyline Developers Limitedpending / no order on file
CC1260384821/06/2026Rupali Hari Khot vs Godrej Skyline Developers Limitedpending / no order on file
CC1260411401/07/2026Anahita Siroos Najmi vs Godrej Skyline Developers Limitedpending / no order on file
CC1260411601/07/2026Priya Santlal Patel vs Godrej Skyline Developers Limitedpending / no order on file
CC1260413802/07/2026Abhishek Gaurishankar Singh vs Godrej Skyline Developers Limitedpending / no order on file
CC1260414102/07/2026Tej Pratap Pandey vs Godrej Skyline Developers Limitedpending / no order on file
CC1260415002/07/2026Ganesh Vidyadhar Nimbargi vs Godrej Skyline Developers Limitedpending / no order on file
CC1260416003/07/2026Parag Arvind Kshirsagar vs Godrej Skyline Developers Limitedpending / no order on file
CC1260417904/07/2026Sumit Ashokrao Umekar vs Godrej Skyline Developers Limitedpending / no order on file
CC1260423106/07/2026Vaibhav Bhagwan Singh Patel vs Godrej Skyline Developers Limitedpending / no order on file
CC1260423406/07/2026Pankaj Krishan Kumar Rajput vs Godrej Skyline Developers Limitedpending / no order on file
CC1260426007/07/2026Snehal Subhashrao Rajurkar vs Godrej Skyline Developers Limitedpending / no order on file
CC1260425307/07/2026Siddhant Sanjay Shah vs Godrej Skyline Developers Limitedpending / no order on file
CC1260426207/07/2026Shadaab Mohiuddin vs Godrej Skyline Developers Limitedpending / no order on file
CC1260439114/07/2026Praveen Omprakash Kumar vs Godrej Skyline Developers Limitedpending / no order on file

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Joint Cjsd And Additional Cjm Pune5932023Closed
Joint Cjsd And Additional Cjm Pune7582023Closed
District Consumer Dispute Redressal Commission Pune22/2942022Pending
Pune District And Sessions Court593/20232023Closed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202530 Mar 2026In view of the application, request developer be granted extension for project timelines from 31st March 2025 to 30th March 2026
30 Mar 202530 Sep 2027In light of the reasons mentioned in our application, requesting you to grant us extension for a period of 1.5 years from 30th March 2026 to 30th September 2027

Location, Land & Connectivity

Located at MAMURDI VILLAGE, Service road to Pune Mumbai Expressway, Kurla, Mumbai Suburban, 412101. Per the filed land record, the plot is bounded to the north by 18M WIDE DP ROAD AND PART S NO 13 PART, to the south by ADJOINING GODREJ PARK GREENS PROJECT, to the east by 18M WIDE PROPOSED DP ROAD and to the west by 18M WIDE PROPOSED DP ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park9 km
Baner–Balewadi belt14 km
Pune Junction / city centre23 km
Pune Int'l Airport (Lohegaon)25 km
Kharadi / EON IT Park28 km
Magarpatta / Hadapsar IT29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Godrej Skyline Developers Limited is the promoter on 8 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Godrej Skyline Developers Limited project & its RERA track record →

Other flagged projects by Godrej Skyline Developers Limited

Godrej Skyline Developers Limited
FlaggedPune
Godrej Skyline Developers Limited
FlaggedPune
Godrej Skyline Developers Limited
FlaggedPune
Godrej Skyline Developers Limited
FlaggedPune
Godrej Skyline Developers Limited
FlaggedPune
Godrej Skyline Developers Limited
FlaggedPune

Other RERA-registered projects in Ravet

Shivratna
possession by Jul 2026 · Mr Rajan Vishram Palekar
Glorious Tathastu
possession by Jul 2026 · Glorious Buildcon
Aqua Life
possession by Aug 2026 · Legacy Lifespaces LLP
City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited

Major developers building in Ravet

Other RERA-registered projects in Pune

Forest Mist
declared completion Mar 2018 · Suraj Raman Bhujbal
Forest Traiils
declared completion Nov 2022 · Champion Builders & Developers
Forest Trails Athashri - B2
declared completion Jul 2024 · Paranjape Schemes Limited
Forest Trails Athashri B3
possession by Sep 2029 · Lavim Developers PVT LTD
Forest Trails Everglades H3 And H4
declared completion Dec 2025 · Paranjape Schemes LTD
Forest Trails Highland Tower 7 And 8
declared completion Mar 2018 · Paranjape Schemes Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026