Pune/Project record

MahaRERA · the public record

Forest Mist

Pune · Suraj Raman Bhujbal

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100010711

Delivery and registration

When is the project declared for completion?

Forest Mist is registered with MahaRERA as P52100010711 and the promoter has declared completion for 31 Mar 2018.

31 Mar 2018

declared completion

102months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100010711
Registered on31 Aug 2017
Promoter-declared completion31 Mar 2018
Current statusCertificate Signed
Against todayabout 102 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Forest Mist record 3 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 3 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Suraj Raman Bhujbal is the promoter of record on 12 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

12projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Forest Mist in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
A1G+13-
B1G+13-

Legal and disputes

What disputes are disclosed?

16 complaints are on the MahaRERA record for Forest Mist, with orders passed in 16 of them.

16complaints

16with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001085411/01/2018NITIN BHASKAR PANDIT vs BHUJBAL BROTHERS CONSTRUCTION COMPANYorder passed
CC00500000001076527/12/2017CHHAYA CHANDRAKANT SHIRAVALE and CHANDRAKANT WAMAN SHIRAVALE vs Mr. Suraj Raman Bhujbal and Ranjit J. Bhujbalorder passed
CC00500000001097525/02/2018SATYANARAYAN TRIMBAK KAMBLE vs BHUJBAL BROTHERS CONSTRUCTION COMPANYorder passed
CC00500000002273606/03/2019Mr. Nitin Anant More vs M/S. Bhujbal Brothers Construction Companyorder passed
CC00500000001111208/04/2018SHALINI BHARAT CHOUDHARY vs BHUJBAL BROTHERS CONSTRUCTION COMPANYorder passed
CC00500000001147528/04/2018ROHIT ASHOK DESHKAR vs SURAJ RAMAN BHUJBALorder passed
CC00500000001147929/04/2018ABHINAV ANIL BORKAR vs SURAJ RAMAN BHUJBALorder passed
CC00500000001174023/12/2018Aniruddha Shashikant Atre vs M/s. Bhujbal Brothers Construction Companyorder passed
CC00500000002242924/01/2019Mr. Yuvaraj Anandrao Lokhande vs M/s. Bhujbal Brothers Construction Companyorder passed
CC00500000002245114/01/2019Mr. Prasad Mirasaheb Kadale vs M/s. Bhujbal Brothers Construction Companyorder passed
CC00500000002275406/03/2019Mr. Sumeet Ramesh Ghodke vs M/s. Bhujbal Brothers Construction Companyorder passed
CC00500000002289615/04/2019Mr. Manjul KumarJha vs M/S. Bhujbal Brothers Construction Companyorder passed
CC00500000002308331/05/2019Raja Abhishek Jain vs M/s. Bhujbal Brothers Construction Companyorder passed
CC00500000002312223/06/2019Mr. Swapnil Shankar Divekar vs M/s. Bhujbal Brothers Construction Companyorder passed
CC00500000006436201/08/2020Nitin Vijaykumar Biyani vs M/s. Bhujbal Brothers Construction Company Through its partner Mr. Suraj Raman Bhujbalorder passed
CC00500000023866317/05/2023Mr Swapneel Subhashchandra Kirtikar vs Bhujbal Brothers Construction Company Through its Partner Mr Dhiraj Raman Bhujbalorder passed

Location, Land & Connectivity

Located at Haveli, Pune, 411028. Per the filed land record, the plot is bounded to the north by s no65, to the south by s no 64 part, to the east by DP road and to the west by Govt Forest. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT5 km
Pune Junction / city centre9 km
Kharadi / EON IT Park9 km
Pune Int'l Airport (Lohegaon)12 km
Baner–Balewadi belt19 km
Hinjewadi Rajiv Gandhi IT Park24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Suraj Raman Bhujbal is the promoter on 3 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Suraj Raman Bhujbal

Suraj Raman Bhujbal
Past its declared completion datePune
Suraj Raman Bhujbal
Past its declared completion datePune

Other RERA-registered projects in Hadapsar

Kumar Parc Residences - A1
possession by Nov 2026 · Kumar Properties Infratech Developers Pv
ARV Royale Phase II
possession by Dec 2026 · Vedant Properties
Amanora Crown Towers
possession by Dec 2026 · City Realty & Development Private Li
Elina Premium
possession by Dec 2026 · Binawat Realty LLP
Freedom High Street
possession by Dec 2026 · Dilip Baburao Tupe
Kohinoor Artize Wing B
possession by Dec 2026 · Shivayogi Kashinath Chikhale

Major developers building in Hadapsar

Other RERA-registered projects in Pune

Forest Traiils
declared completion Nov 2022 · Champion Builders & Developers
Forest Trails Athashri B3
possession by Sep 2029 · Lavim Developers PVT LTD
Forest Trails Everglades H3 And H4
declared completion Dec 2025 · Paranjape Schemes LTD
Forest Trails Highland Tower 7 And 8
declared completion Mar 2018 · Paranjape Schemes Limited
Forest Villa
declared completion Mar 2023 · Tirupati Developers
Foresta
possession by Dec 2028 · Rachit Rahul Agarwal

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026