MahaRERA Property Intelligence · Pune

Pratham Apartments

P52100013785 · promoter Rohan

Certificate SignedDue 31 Mar 2018

Delivery & Registration

MahaRERA registrationP52100013785
Registered on25 Oct 2017
Promoter-declared completion31 Mar 2018
Current statusCertificate Signed
Against todayabout 100 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
Pratham Apartment1G+2-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Haveli, Pune, 411028. Per the filed land record, the plot is bounded to the north by Road, to the south by Sanjay Nhawale Property, to the east by Sr No 36 of 2 and to the west by Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Magarpatta / Hadapsar IT4 km
Kharadi / EON IT Park7 km
Pune Junction / city centre8 km
Pune Int'l Airport (Lohegaon)11 km
Baner–Balewadi belt19 km
Hinjewadi Rajiv Gandhi IT Park24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Rohan Bandu Nhawale project & its RERA track record →

Other RERA-registered projects in Hadapsar

Kumar Parc Residences - A1
possession by Nov 2026 · Kumar Properties Infratech Developers Pv
ARV Royale Phase II
possession by Dec 2026 · Vedant Properties
Amanora Crown Towers
possession by Dec 2026 · City Realty & Development Private Li
Elina Premium
possession by Dec 2026 · Binawat Realty LLP
Freedom High Street
possession by Dec 2026 · Dilip Baburao Tupe
Kohinoor Artize Wing A
possession by Dec 2026 · Shivayogi Kashinath Chikhale

Major developers building in Hadapsar

Other RERA-registered projects in Pune

Pratham Residency
declared completion Dec 2019 · Pratham Realtors
Pratham Vihar Phase I
possession by Mar 2029 · LJR Constructions LLP
Pratham Yash Residency
declared completion Dec 2019 · Pratham Yash Associates
Pratham Yash Residency Phase IV Wing E
declared completion Jun 2023 · Pratham Yash Associates
Pratham Yash Vrindavan
declared completion Jun 2022 · Pratham Yash Builders
Pratham Yash Vrindavan 3
possession by Sep 2027 · Pratham Yash Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.