MahaRERA Property Intelligence · Pune

Lodha Belmondo Townhouse 3

P52100045926 · Gahunje · promoter Lodha

Certificate SignedDue 31 Mar 2026

Delivery & Registration

MahaRERA registrationP52100045926
Registered on15 Jun 2022
Promoter-declared completion31 Mar 2026
Current statusCertificate Signed
Against todayabout 4 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
BLDG 421G+2-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Gahunje, Gahunje Road, Mumbai City, Mumbai City, 412101. Per the filed land record, the plot is bounded to the north by Bldg No 42, to the south by Bldg No 46, to the east by Adj Gat No 269 P and to the west by Internal Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 171 MahaRERA-registered projects, of which 9 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedPune

Other RERA-registered projects in Ravet

Shivratna
possession by Jul 2026 · Mr Rajan Vishram Palekar
Glorious Tathastu
possession by Jul 2026 · Glorious Buildcon
Aqua Life
possession by Aug 2026 · Legacy Lifespaces LLP
City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited

Major developers building in Ravet

Other RERA-registered projects in Pune

Lodha Belmondo - Townhouses
declared completion Jun 2022 · Lodha Developers Limited
Lodha Hinjewadi Phase 3
possession by Jun 2031 · Bellissimo Infratech Private Limited
Lodha Pune Nibm Project
possession by Jul 2026 · Lodha Developers Limited
Lodha Pune Nibm Project-Tower 10
possession by Dec 2026 · Lodha Developers Limited
Lodha Pune Nibm Project-Tower 5
possession by Dec 2026 · Lodha Developers Limited
Lodha Pune Nibm Project-Tower 6
possession by Dec 2026 · Lodha Developers Limited

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026