MahaRERA Property Intelligence · Pune

NISARG

P52100026279 · URULI DEVACHI · promoter Waje Harpale Patil

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP52100026279
Registered on04 Sep 2020
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Waje Harpale Patil is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
NISARG WING A AND WING B1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
07 Aug 202431 Dec 2027The Promoter is not able to Complete the Work and also the promoter is not able to sale all Units in the given time Period due to COVID Pandemic and other reasons. The promoter has

Location, Land & Connectivity

Located at URULI DEVACHI, URULI DEVACHI, Haveli, Pune, 412308. Per the filed land record, the plot is bounded to the north by S NO 155 AND S NO 153, to the south by S NO 281, to the east by S NO 151 AND S NO 157 and to the west by CANOL. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Fursungi

Simplicity Phase 4 - A Wing
possession by Jul 2026 · J K P Developers Unit NO 2
Tranquility Annexe C Wing
possession by Jul 2026 · K AND B Associates
Casalino Towers Phase 3
possession by Oct 2026 · Sai Siddhi Promoters & Builders
Silver Park - B Wing
possession by Dec 2026 · Hakke AND KAD Developers
Green Hive Plus Wing A4
possession by Dec 2026 · Ram India Shelters
Sahara Platinum
possession by Dec 2026 · Sahara Buildtek

Major developers building in Fursungi

Other RERA-registered projects in Pune

Nisarg Ansh
possession by Dec 2026 · Ganesh Vasant Walke
Nisarg B AND C Wing
declared completion Dec 2022 · Dabhade Agarwal Associates
Nisarg City
declared completion Feb 2021 · Yashashri Developers And Builders
Nisarg Human Park
declared completion Aug 2019 · Anil Vasant Sorate
Nisarg Palms
declared completion Jun 2018 · Aditya Shagun Developers
Nisarg Palms
declared completion Dec 2019 · Aditya Shagun Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026