OJAS EYRIE PHASE - 1

NANGARGAON · FRIENDS DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100050302

Delivery and registration

When is the project declared for completion?

OJAS EYRIE PHASE - 1 is registered with MahaRERA as P52100050302 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100050302
Registered on01 Apr 2023
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OJAS EYRIE PHASE - 1 record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Friends Developers is the promoter of record on 19 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

19projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for OJAS EYRIE PHASE - 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
A 31G+231 Dec 2025
E1G+131 Dec 2025
F1G+131 Dec 2025
G1G+131 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NANGARGAON, NANGARGAON ROAD, Mawal, Pune, 410401. Per the filed land record, the plot is bounded to the north by SURVEY NUMBER 22- 23, to the south by 15 METER WIDE ROAD, to the east by 15 METER WIDE ROAD and to the west by SURVEY NUMBER 37 - 1 PART. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Friends Developers is the promoter on 7 MahaRERA-registered projects, of which 5 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Friends Developers project & its RERA track record →

Other RERA-registered projects in Lonavala

Vogue 25
possession by Oct 2026 · Goodbrick Realty Private Limited
Amoda Reserve - South Park
possession by Dec 2026 · Kalpataru Properties Private Limited
Atarkya Apartment
possession by Dec 2026 · Ankush Narayan Chaudhari
Bliss Estates
possession by Dec 2026 · Benjamin Michael Manuel
Hill Spring Enclave 4
Deregistered by MahaRERA · possession by Dec 2026 · S & S Associates
Lonavalas Finest Phase2
possession by Dec 2026 · Rahul Hanumant Satav

Other RERA-registered projects in Pune

Ojas Residency
declared completion Aug 2022 · Vastusankalpa Promoters AND Builders
Ojasvi Gold
declared completion Jun 2025 · Krishna Renuka Realty
Olina
declared completion Jun 2026 · S S Projects
Olive Homes -1
declared completion Jun 2026 · Aakar Realties
Olive Homes - 2
declared completion Jun 2026 · Aakar Realties
Olive ONE
declared completion Jan 2019 · Tamboli Infra Projects Pvt Ltd

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026