PARAMOUNT SMART CITY

P52100001196 · Lohgaon · promoter Amarnath Builders And

Certificate SignedDue 31 Jan 2024

Delivery & Registration

MahaRERA registrationP52100001196
Registered on27 Jul 2017
Promoter-declared completion31 Jan 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Amarnath Builders And is the promoter of record on 15 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
WING E1G+931 Dec 2019
WING B1G+1231 Dec 2019
WING C1G+931 Dec 2019
WING D1G+431 Dec 2019

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000029000606/01/2024Kamal Kumar Ghosh vs AMARNATH BUILDERS & DEVELOPERSorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Pune District Court410/20132013Judgement In Favor Of Developer

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Jan 202431 Dec 2020In our agreement to sale we have mentioned the possession date as December 2019. But due to the less booking of flat of our project have affected our financial strength, hence we a
31 Jan 202429 Dec 2021Project work is in process , project possession date is postpone due to Manpower & Material unavailability. 80% work completed and expected work completion date will be Dec 2021
31 Jan 202431 Jan 20241. As the entire country including Pune District were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures

Location, Land & Connectivity

Located at Lohgaon, Porwal Road, Haveli, Pune, 411047. Per the filed land record, the plot is bounded to the north by 18 MTR RP ROAD, to the south by SURVEY NO 298 PROPERTY OF VIJAY KHANDAVE AND OTHER, to the east by SURVEY NO 298 PROJECT OF KOTHARI AND TINGARE and to the west by SURVEY NO 298 GOYALGANGA BUILDERS AND MR MURKUTE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)3 km
Kharadi / EON IT Park7 km
Pune Junction / city centre9 km
Magarpatta / Hadapsar IT10 km
Baner–Balewadi belt15 km
Hinjewadi Rajiv Gandhi IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Lohegaon

Nivasa Enchante Phase 2
possession by Aug 2026 · Nivasa Associates
Aayush Exotica
possession by Sep 2026 · Aayush Properties
Chandan Heritage
possession by Sep 2026 · City Developers
Youthika
possession by Oct 2026 · Krushnarang Group
Easterlia
possession by Dec 2026 · Spacemint Realty LLP
Pankaj Aasmaan Phase V
possession by Dec 2026 · Pankaj Developers

Major developers building in Lohegaon

Other RERA-registered projects in Pune

Paramsundar
declared completion Dec 2017 · Parte Developers
Paranjape Abhiruchi Parisar -T1,t2 ,t3, M1a, M1B And M2
declared completion Mar 2025 · Paranjape Schemes LTD
Paras Parshwa Nagar II
possession by Dec 2029 · Shree Parshwa Nagar Realty LLP
Paras Shagun
possession by Oct 2027 · Paras Properties
Paras-Vista
declared completion Dec 2021 · Paras Developers
Pardeshi-Darawade Height
declared completion Dec 2024 · Vishal Shankar Pardeshi

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026