MahaRERA Property Intelligence · Pune

Playtor Paud A

P52100001798 · Next to Tehsil Office · promoter Playtor Paud Landmarks

Certificate SignedDue 30 Jun 2018

Delivery & Registration

MahaRERA registrationP52100001798
Registered on29 Jul 2017
Promoter-declared completion30 Jun 2018
Current statusCertificate Signed
Against todayabout 97 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
A11G+730 Jun 2018
A21G+730 Jun 2018
A31G+430 Jun 2018

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000002305120/05/2019GANESH MOHITE vs Playtor paud Landmarks private limitedorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Jr Division Pune6872017Written Statment And Say

Location, Land & Connectivity

Located at Next to Tehsil Office, Paud-Mulshi Road, Pune City, Pune, 412108. Per the filed land record, the plot is bounded to the north by Gat No 227, to the south by Gat No 219 220 221, to the east by Gat No 217 and to the west by Gat No 244. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park15 km
Baner–Balewadi belt18 km
Pune Junction / city centre27 km
Magarpatta / Hadapsar IT33 km
Pune Int'l Airport (Lohegaon)33 km
Kharadi / EON IT Park35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Paud

Foresta Phase II
possession by Aug 2026 · High Yield Fortune Pvt Ltd
Playtor Paud D- Phase 2
Deregistered by MahaRERA · possession by Sep 2026 · Sangam Realty
Shivangan
possession by Nov 2026 · R M Developers Pune
Nishigandh, B Wing
possession by Dec 2026 · Nirmiti Realities
Satvam Hills C4
possession by Dec 2026 · Symphony Landmarks LLP
Sparsh Aster
possession by Dec 2026 · Shree Enterprises

Other RERA-registered projects in Pune

Playtor Paud B
declared completion Mar 2023 · Playtor Paud Homes Private Limited
Playtor Paud C- Phase 1
declared completion Mar 2023 · Sangam Realty
Playtor Paud C- Phase 2
declared completion Jun 2024 · Sangam Realty
Playtor Paud D- Phase 1
declared completion Jun 2023 · Sangam Realty
Playtor Paud D- Phase 2
possession by Sep 2026 · Sangam Realty
Playtor Rajgurunagar- Phase 2
declared completion Mar 2023 · Playtor Rajgurunagar Developers Private

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026