PRATHAMESH

KHADAKWASALA · ASHOK PAWAR GROUP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100007482

Delivery and registration

When is the project declared for completion?

PRATHAMESH is registered with MahaRERA as P52100007482 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100007482
Registered on17 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PRATHAMESH record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PRATHAMESH in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
PRATHAMESH1G+13-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for PRATHAMESH, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000002272027/02/2019MOHAN HANUMANT MATE vs M/s Ashok Pawar Grouporder passed

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 3 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court13779/182018Pending
Cjsd Pune100/20182018Disposed
Bombay High Court250/202020Pending
Cjsd Pune436/20192019Pending

Location, Land & Connectivity

Located at KHADAKWASALA, SINHGAD ROAD, Pune City, Pune, 411041. Per the filed land record, the plot is bounded to the north by MAIN SINGHGAD ROAD, to the south by SURVEY NO 18 HISSA NO 16 OF 14, to the east by SURVEY NO 18 HISSA NO 1 OF 3 AND 9 OF 3 and to the west by SURVEY NO 18 HISSA NO 11 OF 1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~88 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park88 km
Baner–Balewadi belt93 km
Pune Junction / city centre104 km
Pune Int'l Airport (Lohegaon)106 km
Kharadi / EON IT Park109 km
Magarpatta / Hadapsar IT110 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhayari

Aqura Pride
possession by Sep 2026 · Aqura Builder And Developer Private Limi
Majestique Swapnangan Wing A And Wing B
possession by Sep 2026 · Majestique Horizon LLP
Tridal Samruddhi
possession by Sep 2026 · M/s. Tridal Associates
Vasant Vihar A Wing
possession by Sep 2026 · A R Developers
Homedale
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Navjyot Abha Phase II B And D
Not filing quarterly progress reports · possession by Dec 2026 · Sumeru Buildcon Private Limited

Major developers building in Dhayari

Other RERA-registered projects in Pune

Prathamesh 4 Ekdanat Residency
declared completion Mar 2019 · Vastu Developers AND Builders
Prathamesh Aakruti
possession by Dec 2028 · Prathamesh Constructions
Prathamesh Anant Building OF Bhargav CHS LTD
declared completion Jun 2023 · Prathamesh Constructions
Prathamesh Apartment
possession by Aug 2027 · Skyline Enterprises
Prathamesh Aura 1
declared completion Mar 2026 · Archana Abhay Mandhare
Prathamesh Aura 2
declared completion Mar 2026 · Arvind Rangnath Mandhare

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026