Pune/Project record

MahaRERA · the public record

Prerita Heights

Bopkhel · Krushnarang Realities

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100019870

Delivery and registration

When is the project declared for completion?

Prerita Heights is registered with MahaRERA as P52100019870 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100019870
Registered on07 Mar 2019
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Prerita Heights record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Krushnarang Realities is the promoter of record on 6 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Prerita Heights in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Prerita Heights Building A1G+531 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Bopkhel, Colony no 10 , Ganeshnagar, Haveli, Pune, 411031. Per the filed land record, the plot is bounded to the north by Property of K N Bhatti, to the south by 4m proposed road, to the east by Property of same S No 148 and to the west by Property of MrFutane. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)6 km
Pune Junction / city centre7 km
Kharadi / EON IT Park9 km
Baner–Balewadi belt10 km
Magarpatta / Hadapsar IT11 km
Hinjewadi Rajiv Gandhi IT Park13 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bopkhel

Ghule Pride
possession by Sep 2026 · Shravya Developers
IRA Icon
possession by Sep 2026 · Tirupati Associates
Swami Shrushti
possession by Dec 2026 · Pruthviraj Developers Through Sagar Hanu
Crystal Space
possession by Mar 2027 · SAI Samarth Developers
Kundan Praangan
possession by Mar 2027 · Kundan AND Jain Developers LLP
Aksha Casa Palladium
possession by May 2027 · Accurate Realities

Other RERA-registered projects in Pune

Presidency Towers
declared completion Jun 2026 · Presidency Hospitality Limited
President Park
possession by Dec 2030 · Sindhu Developers
Presidentia
declared completion Dec 2025 · Yellowstone Skyscrapers LLP
Presidential Park Phase 1
declared completion Dec 2025 · Oneness Realtors
Presidential Park Phase 2
possession by Oct 2026 · Oneness Realtors
Presidential Tower
possession by Dec 2026 · Govind Raviraj Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026