Pune/Project record

MahaRERA · the public record

RAJYOG RESIDENCY

SWAMI VIVEKANAND NAGAR BEHIND RAYALKAR HOSPITAL · BALAJI VIKRAM AWARE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014835

Delivery and registration

When is the project declared for completion?

RAJYOG RESIDENCY is registered with MahaRERA as P52100014835 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014835
Registered on08 Jan 2018
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAJYOG RESIDENCY record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAJYOG RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
RESIDENTIAL1G+431 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at SWAMI VIVEKANAND NAGAR BEHIND RAYALKAR HOSPITAL , SAMBHAJI NAGAR, Haveli, Pune, 412201. Per the filed land record, the plot is bounded to the north by 9 M EXISTING ROAD, to the south by OLD SR NO 8-2, to the east by PLOT NO 67 and to the west by PLOT NO 65. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~160 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park160 km
Baner–Balewadi belt165 km
Pune Int'l Airport (Lohegaon)173 km
Pune Junction / city centre174 km
Kharadi / EON IT Park177 km
Magarpatta / Hadapsar IT179 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Loni Kalbhor

Arvan Residency
possession by Dec 2026 · Sanskruti Developers
Keshavyog Residency
possession by Dec 2026 · Siddhivinayak Builders
Muktai Park Phase II
possession by Dec 2026 · Shivshakti Buildcon
Platinum Nirvana
possession by Dec 2026 · Platinum Developers
Swami Homes
possession by Jan 2027 · S S Developers
Krishnai Residency
possession by Mar 2027 · Ivana Properties

Other RERA-registered projects in Pune

Rajyog Royal
declared completion Jun 2021 · Rajyog Builders And Developers
Rajyog Vitthal
declared completion Jan 2026 · Vitthal Properties
Rakhi
possession by Oct 2028 · Ranjekar Realty LLP
Rakshak Vatika A B C Wings
declared completion Jun 2024 · Urban Life Realty LLP
Rakshe Biz Icon
possession by Dec 2028 · Rakshe Biz Icon Private Limited
RAM Kanta Apartments
declared completion Jun 2026 · Phadtare Buildcon

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026