MahaRERA Property Intelligence · Pune

RANJAI

P52100015162 · Behind Anant Mangal Karyalay · promoter Shinde Patil Construction

Certificate SignedDue 31 Mar 2026

Delivery & Registration

MahaRERA registrationP52100015162
Registered on02 Feb 2018
Promoter-declared completion31 Mar 2026
Current statusCertificate Signed
Against todayabout 4 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shinde Patil Construction is the promoter of record on 113 projects, of which 24 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~83.3% of the estimated project cost incurred as of the last certificate (₹11.89 Cr spent against a ₹14.27 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~83.3% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 90 homes filed with MahaRERA, 50 are sold/booked and 40 remain available (~56% sold) — selling steadily. Buyers have committed ₹15.13 Cr in agreement value so far. Of that, ₹11.81 Cr (~78%) is already collected, ₹3.02 Cr receivable — a read on how far along these sales really are. Note: the project registers 96 homes in total, but this sold/unsold inventory filing covers only 90 of them — the other 6 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 50 registered agreements, the effective carpet rate is ₹5,696/sqft (typical range ₹4,536–₹6,979) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1Flat no. 104626 sqft (58.18 sqm)₹35.67 Lakh
Floor 1Flat no. 105610 sqft (56.69 sqm)₹34.76 Lakh
Floor 1Flat no. 106626 sqft (58.18 sqm)₹35.67 Lakh
Floor 1Flat no. 107443 sqft (41.17 sqm)₹25.24 Lakh
Floor 2Flat no. 203443 sqft (41.17 sqm)₹25.24 Lakh
Floor 2Flat no. 204626 sqft (58.18 sqm)₹35.67 Lakh
Floor 2Flat no. 205610 sqft (56.69 sqm)₹34.76 Lakh
Floor 2Flat no. 206626 sqft (58.18 sqm)₹35.67 Lakh
Floor 3Flat no. 303443 sqft (41.17 sqm)₹25.24 Lakh
Floor 3Flat no. 304626 sqft (58.18 sqm)₹35.67 Lakh
Floor 3Flat no. 305610 sqft (56.69 sqm)₹34.76 Lakh
Floor 3Flat no. 306626 sqft (58.18 sqm)₹35.67 Lakh
Floor 4Flat no. 403443 sqft (41.17 sqm)₹25.24 Lakh
Floor 4Flat no. 404626 sqft (58.18 sqm)₹35.67 Lakh
Floor 4Flat no. 405610 sqft (56.69 sqm)₹34.76 Lakh
Floor 4Flat no. 406626 sqft (58.18 sqm)₹35.67 Lakh
Floor 5Flat no. 504626 sqft (58.18 sqm)₹35.67 Lakh
Floor 5Flat no. 505610 sqft (56.69 sqm)₹34.76 Lakh
Floor 6Flat no. 603443 sqft (41.17 sqm)₹25.24 Lakh
Floor 6Flat no. 604626 sqft (58.18 sqm)₹35.67 Lakh
Floor 6Flat no. 607443 sqft (41.17 sqm)₹25.24 Lakh
Floor 7Flat no. 701487 sqft (45.26 sqm)₹27.75 Lakh
Floor 7Flat no. 703443 sqft (41.17 sqm)₹25.24 Lakh
Floor 8Flat no. 801487 sqft (45.26 sqm)₹27.75 Lakh
Floor 8Flat no. 802626 sqft (58.18 sqm)₹35.67 Lakh
Floor 8Flat no. 803443 sqft (41.17 sqm)₹25.24 Lakh
Floor 8Flat no. 806626 sqft (58.18 sqm)₹35.67 Lakh
Floor 8Flat no. 807443 sqft (41.17 sqm)₹25.24 Lakh
Floor 9Flat no. 902676 sqft (62.83 sqm)₹38.52 Lakh
Floor 9Flat no. 903443 sqft (41.17 sqm)₹25.24 Lakh
Floor 9Flat no. 904626 sqft (58.18 sqm)₹35.67 Lakh
Floor 9Flat no. 905610 sqft (56.69 sqm)₹35.76 Lakh
Floor 9Flat no. 906626 sqft (58.18 sqm)₹35.67 Lakh
Floor 9Flat no. 907443 sqft (41.17 sqm)₹25.24 Lakh
Ground/Floor 0Shop no. 1250 sqft (23.2 sqm)₹17.47 Lakh
Ground/Floor 0Shop no. 2304 sqft (28.26 sqm)₹21.29 Lakh
Ground/Floor 0Shop no. 3250 sqft (23.2 sqm)₹17.47 Lakh
Ground/Floor 0Shop no. 4227 sqft (21.11 sqm)₹15.90 Lakh
Ground/Floor 0Shop no. 5236 sqft (21.9 sqm)₹15.88 Lakh
StiltFlat no. 3626 sqft (58.18 sqm)₹35.67 Lakh

⚠ The inventory filing also declares: 6 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9 and 96 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
RANJAI1G+996-

Unit mix on the filing: 87 residential and 9 non-residential (shops/offices).

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000025883209/05/2023Omkar Jagtap vs Shinde & Patil Constructionorder passed
CC1250330816/09/2025Tejas Rajendra Sawant vs Shinde & Patil Constructionorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 5 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202429 Apr 2024Non availability of labours and the construction material because of Covid-19 Pandemic.
31 Dec 202431 Dec 2024The delay is caused due to getting the plans revised from the Competent Authority
30 Apr 202331 Jul 2025The delay for completing the said project is caused due to permission from the PMC for further floors was not granted for 2.5 yrs and after 2.5 yrs PMC granted the further permissi
30 Apr 202331 Dec 2025The delay for completing the said project is caused due to permission from the PMC for further floors was not granted for 2.5 yrs and after 2.5 yrs PMC granted the further permissi
30 Apr 202331 Mar 2026The delay for completing the said project is caused due to permission from the PMC for further floors was not granted for 2.5 yrs and after 2.5 yrs PMC granted the further permissi

Location, Land & Connectivity

Located at Behind Anant Mangal Karyalay, -, Haveli, Pune, 411023. Per the filed land record, the plot is bounded to the north by Mr Rajesh Gaikwad Property, to the south by 9 mtr Road, to the east by Mr Javalkar Mr Dangat Mr Shitkal Property and to the west by Mr Vijay Gaikwad Property. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Baner–Balewadi belt11 km
Pune Junction / city centre13 km
Hinjewadi Rajiv Gandhi IT Park15 km
Magarpatta / Hadapsar IT17 km
Kharadi / EON IT Park20 km
Pune Int'l Airport (Lohegaon)20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shivane

Kumar Prakruti
possession by Oct 2026 · Kumar Properties Govind Shree Realtors L
Sai Orchid
possession by Oct 2026 · M/S Rudra Builders AND Developers
Aldea Annexo -C1
possession by Dec 2026 · Puranik Builders Limited
Audumbar Nest
possession by Dec 2026 · Om Chidanand Developers
Dongar Maatha
possession by Dec 2026 · M/s Starlight Projects
Sajan Siddhi D Wing
possession by Dec 2026 · Nemichand Bhandari Associates

Major developers building in Shivane

Other RERA-registered projects in Pune

Ranjan Heights-A Wing
declared completion Dec 2021 · Ranu Mahadu Bhondve
Ranjan Heights- Wing B
declared completion Dec 2025 · Ranu Mahadu Bhondve
Ranjeet Heights CO OP HSG Society
declared completion Oct 2023 · Rajesh Dinesh Vyas
Rasik
declared completion Jun 2024 · Pandit Javdekar Associates
Ratan Heights
possession by Dec 2028 · Dipti Harshata Construction
Ratan Neptune Phase 2
declared completion Dec 2018 · Ratan Housing Development Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026