MahaRERA Property Intelligence · Pune

River View Residency

P52100010996 · promoter Balaji Group

Certificate SignedDue 25 Dec 2022

Delivery & Registration

MahaRERA registrationP52100010996
Registered on31 Aug 2017
Promoter-declared completion25 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Building C1G+6-
Building B1G+6-
Building A1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Pune City, Pune, 411052. Per the filed land record, the plot is bounded to the north by Road, to the south by 25 P, to the east by 25 part open area and to the west by Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre8 km
Baner–Balewadi belt10 km
Magarpatta / Hadapsar IT12 km
Hinjewadi Rajiv Gandhi IT Park15 km
Kharadi / EON IT Park15 km
Pune Int'l Airport (Lohegaon)16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Karve Nagar

Ganga Lahari CO-Operative Housing Society LTD
possession by Oct 2026 · M/S Gokhale Constructions
Gomati Narmada Chsl
possession by Dec 2026 · Kotibhaskar Infrastructures &develop
LE Skylark
possession by Dec 2026 · Kakade Green Estates Private Limited
Anika Gokul Niwas
possession by Dec 2026 · Not Available
Ekdant
possession by Dec 2026 · Swojas Icon Associates LLP
Saukhyam
possession by Apr 2027 · Ranjekar Sahasrabudhe LLP

Other RERA-registered projects in Pune

River Vista
possession by Mar 2028 · Rahul Shubham LLP
Rivera
possession by Dec 2029 · Ekansh Buildcon LLP
Rivera Residence Phase 1
possession by Dec 2029 · M/s High Yield Fortune Pvt Ltd
Riverain Classic
possession by Dec 2026 · Belvalkar Housing Company
Riverdale Avenue
declared completion Oct 2025 · Duville Estates Private Limited
Riverdale Grand
possession by Sep 2028 · Duville Estates Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026