Pune/Project record

MahaRERA · the public record

S3 RESINDENCES

Chikhali · JANHVI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014470

Delivery and registration

When is the project declared for completion?

S3 RESINDENCES is registered with MahaRERA as P52100014470 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014470
Registered on04 Dec 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for S3 RESINDENCES record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for S3 RESINDENCES in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
S3 Residences1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Chikhali, Zenda Chowk, Haveli, Pune, 411062. Per the filed land record, the plot is bounded to the north by Property of Kulkarni Kadam, to the south by PCMC Road, to the east by Propert of Dashrath Piraji More and to the west by PCMC Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)9 km
Baner–Balewadi belt11 km
Pune Junction / city centre12 km
Hinjewadi Rajiv Gandhi IT Park13 km
Kharadi / EON IT Park13 km
Magarpatta / Hadapsar IT16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chikhali

Elite 28
possession by Sep 2026 · Anita Mahadev Giri
Parshwa Solitaire
possession by Sep 2026 · Parshwa Realtors
Swaroop Homes
Not filing quarterly progress reports · possession by Nov 2026 · Swaroop Homes LLP
North East Business Centre
possession by Nov 2026 · Shiv Properties
Vijay Residency
possession by Dec 2026 · Rudra Infra
Akashvedh Phase 2
possession by Dec 2026 · Raghvendra Buildcon

Other RERA-registered projects in Pune

S3 Supreme
declared completion Feb 2026 · S-3 Properties
Saachee Elite
declared completion Aug 2026 · Suyog Suryakant Chhajed
Saachee ERA
declared completion Dec 2021 · Saachee Group And Superior Spaces
Saajgiri
possession by Aug 2029 · Nanded City Development & Constructi
Saakaar Centrum
possession by Dec 2026 · Saakaar Corporation
Saanes Samrudha Appartments
declared completion Mar 2025 · Ravi Somjibhai Patel

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026