MahaRERA Property Intelligence · Pune

SAHIL HEIGHTS A1

P52100054948 · PIMPLE NILAKH · promoter Vaishnavi

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP52100054948
Registered on21 Feb 2024
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vaishnavi is the promoter of record on 75 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~70.9% of the estimated project cost incurred as of the last certificate (₹15.98 Cr spent against a ₹22.53 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 71 homes filed with MahaRERA, 13 are sold/booked and 58 remain available (~18% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹9.10 Cr in agreement value so far. Of that, ₹6.18 Cr (~68%) is already collected, ₹2.92 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 13 registered agreements, the effective carpet rate is ₹9,639/sqft (typical range ₹8,172–₹11,574) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 71 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SAHIL HEIGHTS A11G+1071-

Unit mix on the filing: 51 residential and 20 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at PIMPLE NILAKH, PIMPLE NILAKH, Haveli, Pune, 411027. Per the filed land record, the plot is bounded to the north by BY DEFENSE LAND, to the south by BY ROAD, to the east by BY PROPERTY OF MR VILAS NANDGDE and to the west by BY PROPERTY OF MR CHONDE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt2 km
Hinjewadi Rajiv Gandhi IT Park5 km
Pune Junction / city centre11 km
Pune Int'l Airport (Lohegaon)14 km
Magarpatta / Hadapsar IT16 km
Kharadi / EON IT Park17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vaishnavi Promoters AND Developers is the promoter on 10 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Vaishnavi Promoters AND Developers project & its RERA track record →

Other flagged projects by Vaishnavi Promoters AND Developers

Vaishnavi Promoters AND Developers
FlaggedPune
Vaishnavi Promoters AND Developers
FlaggedPune
Vaishnavi Promoters AND Developers
FlaggedPune
Vaishnavi Promoters AND Developers
FlaggedPune
Vaishnavi Promoters AND Developers
FlaggedPune
Vaishnavi Promoters AND Developers
FlaggedPune

Other RERA-registered projects in Pimple Nilakh

S3 Lifestyle
possession by Jul 2026 · Siddhivinayak Kohinoor Ventures
Audumber Residency
possession by Aug 2026 · Shama Construction Through Properiter Vi
Sai Neel
possession by Sep 2026 · Vishal Anil Khairnar
Marigold Calendula
possession by Sep 2026 · Audumbar Homes LLP
Sai Aura
possession by Sep 2026 · WJV Landmarks LLP
Sky 2 Cosmos
possession by Oct 2026 · Emperos Properties

Major developers building in Pimple Nilakh

Other RERA-registered projects in Pune

Sahil OM Park
declared completion Dec 2022 · Vaishnavi Promoters AND Developers
Sahil Pride
declared completion Jun 2022 · Yogesh Omprakash Agarwal
Sahil Vatika
possession by Dec 2028 · Yogesh Omprakash Agarwal
Sahil Vighnesh Residency
declared completion Dec 2021 · Vaishnavi Promoters AND Developers
Sahil Yashika
declared completion Jun 2023 · Yogesh Omprakash Agarwal
Sahyadri
possession by Aug 2027 · Sahyadri Builders And Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026