SAHYADRI CITY

P52100013642 · Nasrapur · promoter Om Associates

Certificate SignedDue 30 Apr 2023

Delivery & Registration

MahaRERA registrationP52100013642
Registered on16 Oct 2017
Promoter-declared completion30 Apr 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
A41G+730 Apr 2022
A51G+730 Apr 2022
A61G+730 Apr 2022
B11G+730 Apr 2022
C11G+230 Apr 2022

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00500000001109927/02/2018CC005000000011099 vs popat narayan sukeorder passed
CC00500000006491207/12/2020MAHESHKUMAR MAHADEV MANE vs POPAT NARAYAN SUKEorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Apr 202330 Apr 202180% work has been completed, however, remaining work has under work is going on.
30 Apr 202330 Apr 20211) We have not got completion certificate from competent authority till date. 2) Booking status is not satisfactory to raise the funds for construction. 3) Due amounts from flat ho
30 Apr 202330 Apr 2023In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r

Location, Land & Connectivity

Located at Nasrapur, Nasrapur, Haveli, Pune, 412213. Per the filed land record, the plot is bounded to the north by SHRI DEVSINGH SOLANKI PROPERTY, to the south by SHRI ROHIDAS DALVI PROPERTY, to the east by SHRI RAMESH SHANKAR KADAM PROPERTY and to the west by NASARAPUR VELHE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~30 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Magarpatta / Hadapsar IT30 km
Pune Junction / city centre31 km
Kharadi / EON IT Park34 km
Baner–Balewadi belt36 km
Pune Int'l Airport (Lohegaon)37 km
Hinjewadi Rajiv Gandhi IT Park41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

OM Associates is the promoter on 11 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every OM Associates project & its RERA track record →

Other flagged projects by OM Associates

Other RERA-registered projects in Nasrapur

N 1 Prima
possession by Nov 2028 · Nevara Developers
Swapnalok Township Amenity Building
possession by Mar 2029 · Swapnalok Developers
Ishaan Gharkul A
declared completion Dec 2025 · Ishaan Buildcon
Vastu Appartments
declared completion Jul 2022 · Vastu Developers
Sacramento Valley
Past its declared completion date · declared completion Jun 2021 · Rohit Gardens Pvt. Ltd.
Suman Kalavishwa
Past its declared completion date · declared completion Jan 2021 · Prathamesh Developers Promoters & Bu

Other RERA-registered projects in Pune

Sahyadri Complex
possession by Dec 2026 · Luxuriant Group
Sahyadri Heights
declared completion May 2025 · V. K. Developers
Sahyadri Heights
possession by Jul 2028 · Not Available
Sahyadri Plumeria
possession by Dec 2027 · Sahyadri Landmarks
Sahyadri Plumeria Phase II
possession by Dec 2028 · Sahyadri Landmarks
Sahyadri Pride Pune
possession by Dec 2026 · Dnyanadev Shyamrao Kondhalkar

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026