MahaRERA Property Intelligence · Pune

SAI LEELA

P52100027724 · CHIKHALI · promoter Shivling Vasant Jare

Certificate SignedDue 30 Jun 2023

Delivery & Registration

MahaRERA registrationP52100027724
Registered on03 Jan 2021
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shivling Vasant Jare is the promoter of record on 2 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
SAI LEELA1G+1031 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at CHIKHALI, NEAR SANE CHOWK, Haveli, Pune, 411062. Per the filed land record, the plot is bounded to the north by BELONGS TO BHIKAJI SALVI, to the south by REMAINING PROPERTY OF GAT 1323, to the east by BELONG TO ROAD and to the west by BELONG TO BASAWRAJ BIRAJDAR AND MALKAPPA. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shivling Vasant Jare is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Shivling Vasant Jare

Other RERA-registered projects in Chikhali

Elite 28
possession by Sep 2026 · Anita Mahadev Giri
Parshwa Solitaire
possession by Sep 2026 · Parshwa Realtors
Swaroop Homes
Not filing quarterly progress reports · possession by Nov 2026 · Swaroop Homes LLP
North East Business Centre
possession by Nov 2026 · Shiv Properties
Vijay Residency
possession by Dec 2026 · Rudra Infra
Akashvedh Phase 2
possession by Dec 2026 · Raghvendra Buildcon

Major developers building in Chikhali

Other RERA-registered projects in Pune

SAI Luxuria
declared completion Dec 2022 · Vinod Kishanchand Matani
SAI Magnus
declared completion Dec 2024 · Omshree Associates
SAI MAI Mansion
declared completion Oct 2025 · SAI RAJ Developers
SAI Majestic
declared completion Dec 2017 · S S Developers
SAI Majestic
declared completion Sep 2022 · M/S Shree Bhairavnath Developers
SAI Malhar
declared completion Mar 2019 · Sai Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026