Sai Mauli

Ale · VARADVINAYAK BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100021810

Delivery and registration

When is the project declared for completion?

Sai Mauli is registered with MahaRERA as P52100021810 and the promoter has declared completion for 30 Jun 2025.

30 Jun 2025

declared completion

15months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100021810
Registered on29 Jul 2019
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 15 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sai Mauli record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Varadvinayak Builders is the promoter of record on 14 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

14projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sai Mauli in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Sai Mauli1G+531 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Ale, ., Junnar, Pune, 412411. Per the filed land record, the plot is bounded to the north by 9 mtr wide road, to the south by Open Space, to the east by Rest House and to the west by Plot No 51 and 53. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~72 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)69 km
Kharadi / EON IT Park72 km
Hinjewadi Rajiv Gandhi IT Park76 km
Magarpatta / Hadapsar IT76 km
Pune Junction / city centre76 km
Baner–Balewadi belt77 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Varadvinayak Builders AND Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Varadvinayak Builders AND Developers

Varadvinayak Builders AND Developers
FlaggedPune

Other RERA-registered projects in Alephata

Manas Residency
possession by Dec 2026 · Oorjitaa Realtors
Shree Dattatraya Apartment
possession by Mar 2027 · Kalpana Ankush Gopale
Sai Shrusti
possession by Jul 2027 · Eknath Bhau Shinde
SAI Amrut
Not filing quarterly progress reports · possession by Aug 2027 · Kulswami Builders AND Developers
Shinde Residency
possession by Dec 2027 · Shinde Developers
Time City
Past its declared completion date · possession by Dec 2027 · Sudhir Maruti Narawade

Other RERA-registered projects in Pune

Sai Mehar
possession by Dec 2027 · Sacho Satram Reality LLP
SAI Millenium
declared completion Apr 2025 · Shiv Constructions
Sai Millenium AS
declared completion Sep 2023 · Shiv Constructions
SAI Miracle
declared completion Dec 2019 · SAI Datta Developers
SAI Moreshwar Villas
declared completion Dec 2023 · Maatoshree Shelters PVT LTD
Sai Mudra
possession by Mar 2027 · Fortune Realty

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026