SAI SHRUSHTI

Sate Nagar Velu KASURADI ROAD · Shree Balaji Pramotors and Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100018365

Delivery and registration

When is the project declared for completion?

SAI SHRUSHTI is registered with MahaRERA as P52100018365 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100018365
Registered on26 Oct 2018
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI SHRUSHTI record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Shree Balaji Pramotors is the promoter of record on 5 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI SHRUSHTI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
sai shrushti1G+1731 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2025Due to covid 19 and unavailability of resources.

Location, Land & Connectivity

Located at Sate Nagar Velu KASURADI ROAD, MAIN ROAD GOATAN NEAR, Pune City, Pune, 412205. Per the filed land record, the plot is bounded to the north by GAT 464, to the south by Remaing gat 465 aGAT 466 467 468 COMMAN RAOD 9 MTR, to the east by GAT 467 and to the west by GAT 466. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Magarpatta / Hadapsar IT18 km
Pune Junction / city centre19 km
Kharadi / EON IT Park23 km
Baner–Balewadi belt24 km
Pune Int'l Airport (Lohegaon)25 km
Hinjewadi Rajiv Gandhi IT Park29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kapurhol

Royal Purandar
possession by Dec 2026 · Carcanet Infra Projects Private Limited
Shree Venkatesh SAI Residency
Not filing quarterly progress reports · possession by Mar 2027 · Shree Venkatesh SAI Associates
Balaji Dham Phase-1
possession by Mar 2027 · Garva Land Deal Private Limited
Industree
possession by Feb 2028 · Dhankawade Square Realtors LLP
Navkar Pleasure
possession by Dec 2028 · Parag Properties
Pooja Heavan Park
possession by Dec 2028 · Pooja Developers

Other RERA-registered projects in Pune

SAI Shrushti
declared completion Dec 2025 · SAI Construction
Sai Shrushti
possession by Jul 2030 · Sai Samarth Developers
Sai Shrusti
possession by Jul 2027 · Eknath Bhau Shinde
SAI Shwet
declared completion Dec 2022 · Chandrakant Gulabrao Kokate
SAI Siddhi
declared completion Dec 2020 · S D Developers
SAI Siddhi Residency
declared completion Aug 2023 · SAI Siddhi Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026