Pune/Project record

MahaRERA · the public record

Sai sparsh

Ambegaon · SAI RACHANA LIFESPACES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100021019

Delivery and registration

When is the project declared for completion?

Sai sparsh is registered with MahaRERA as P52100021019 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100021019
Registered on27 May 2019
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sai sparsh record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sai sparsh in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
A WING1G+11-
B WING1G+11-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2024DUE TO COVID-19 SITUATION WE TOOK BOOKINGS ONLY FOR A BUILDING AND HENCE WE HAVE COMPLETED A BUILDING WORK. ALSO THE WORK OF B BUILDING IS 45% COMPLETED AND WE NEED MORE TIME TO CO
31 Dec 202431 Dec 2025we are pleased to inform you that 100% of the construction work for the project has been successfully completed as per the approved plans and standards. however the project has be

Location, Land & Connectivity

Located at Ambegaon , pune mumbai road, Haveli, Pune, 411046. Per the filed land record, the plot is bounded to the north by kondhare plot, to the south by Road, to the east by Sopan bhange plot and to the west by ambar park society. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Junction / city centre9 km
Magarpatta / Hadapsar IT11 km
Baner–Balewadi belt13 km
Kharadi / EON IT Park15 km
Pune Int'l Airport (Lohegaon)16 km
Hinjewadi Rajiv Gandhi IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambegaon Bk

Amits Bloomfield Phase III - J AND K Building
possession by Sep 2026 · Amit Enterprises Housing Limited
Ankur Residency
possession by Oct 2026 · Ankur Developers
Astonia Royale Phase III - P Building
possession by Oct 2026 · Amit Enterprises Housing Limited
Airavat B Wing
possession by Nov 2026 · Ashtavinayak Developers
Rajyog C Wing
possession by Dec 2026 · Santosh Shankar Tathe
Deveshwar Tekadi- Phase I- Building: A,b,c,d,e
Not filing quarterly progress reports · possession by Dec 2026 · Mahadrishti Spaces LLP

Major developers building in Ambegaon Bk

Other RERA-registered projects in Pune

Sai Sparsh
possession by May 2028 · Vaishnavi Developers & Builders
SAI Sparsh
possession by Dec 2027 · SAI Developers
Sai Sparsha3,a4
declared completion Jun 2024 · Jalan Associates
SAI Square
declared completion Aug 2025 · SAI Square
SAI Srushti
possession by Dec 2027 · Ashok Nirman Developers
SAI Stella
possession by Dec 2028 · M/s.shree Sai Capstone

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026