Pune/Project record

MahaRERA · the public record

Sai Vatika - Nishigand

Chandkhed · ABHILASHA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100030261

Delivery and registration

When is the project declared for completion?

Sai Vatika - Nishigand is registered with MahaRERA as P52100030261 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100030261
Registered on10 Aug 2021
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sai Vatika - Nishigand record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Abhilasha Developers is the promoter of record on 20 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

20projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sai Vatika - Nishigand in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Nishigandh1G+431 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2023To, Maharashtra Real Estate Regulatory Authority, Housefin Bhavan, Plot No. C – 21, E – Block, Bandra Kuria Complex, Bandra (E), Mumbai 400051 Sub – Project Extension

Location, Land & Connectivity

Located at Chandkhed, chandkhed, Mulshi, Pune, 410507. Per the filed land record, the plot is bounded to the north by Internal Road, to the south by Gat no 634, to the east by Internal Road and to the west by Plot no 3 part. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Abhilasha Developers is the promoter on 9 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Abhilasha Developers project & its RERA track record →

Other flagged projects by Abhilasha Developers

Other RERA-registered projects in Talegaon Dabhade

Hillcrest
possession by Oct 2026 · Swapnashilp Buildcon
Greendale ENA
possession by Dec 2026 · M/s. Karpe Construction Company
Indraprasth
possession by Dec 2026 · J V Buildcon
Krishna Mahel
Deregistered by MahaRERA · possession by Dec 2026 · Mahesh Developers Ltd
Panoramaa
possession by Dec 2026 · Kakade Properties
SAI Ganesh
possession by Dec 2026 · Aditya Developers

Major developers building in Talegaon Dabhade

Other RERA-registered projects in Pune

SAI Velocity II
possession by Dec 2027 · Prakash Pandurang Chavan
SAI Vihar
declared completion Jan 2021 · Shree Sai Construction
Sai Vilasita
possession by Jun 2028 · Golden Terrain Infra LLP
SAI Villa
declared completion Dec 2021 · JSK Associates
Sai Village
declared completion Dec 2019 · Sai Raj Developers
Sai Vinay
declared completion Dec 2025 · Vinayak Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026