MahaRERA Property Intelligence · Pune
P52100018259 · Rajgurunagar · promoter Agasti Developers
| MahaRERA registration | P52100018259 |
| Registered on | 22 Oct 2018 |
| Promoter-declared completion | 31 Dec 2025 |
| Current status | Certificate Signed |
| Against today | about 7 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| SAIPLAZA | 1 | G+6 | - |
1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC005000000340734 | 07/04/2024 | Mr. Mahesh Kashinath Deshmukh vs M/s. Agasti Developers Through its partner Mr. Lakshmikant Ambadas Naikwadi | order passed |
The promoter has had the MahaRERA completion deadline formally extended 5 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 31 Mar 2020 | 31 Mar 2024 | Construction of the project is almost completed and we have already applied for part completion certificate but due to some RTI applications and transfer of concerns officials , co |
| 31 Mar 2020 | 31 Dec 2024 | Dear Authority, We have already completed the construction part and have applied for occupancy certificate but same is pending due to "Mojani Notice" from Bhumi Abhilesh Vibhag, Ma |
| 31 Mar 2020 | 31 Mar 2021 | No of days Mansoon stayed in West Maharasthra in FY 2019-20 were quite large as compared to average days. This resulted into delay in construction progress. No of permissions and s |
| 31 Mar 2020 | 31 Mar 2025 | We hereby submit this request to kindly grant an extension of three months for the completion timeline of our project [Project Name] registered under RERA with Registration No. P5 |
| 31 Mar 2020 | 31 Dec 2025 | We had applied for extension up to 31/12/2025 in previous application in FORM B but at the time of filing the online application we had selected 31/03/2025 as the extension date by |
Located at Rajgurunagar, Pune Nashik Highway, Khed, Pune, 410505. Per the filed land record, the plot is bounded to the north by Mr Chavan and Dr Bamble Property, to the south by Old Pune Nashik Highway, to the east by By New Pune Nashik Highway and to the west by Old Pune Nashik Highway. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Pune Junction / city centre | 2 km |
| Magarpatta / Hadapsar IT | 7 km |
| Kharadi / EON IT Park | 9 km |
| Baner–Balewadi belt | 9 km |
| Pune Int'l Airport (Lohegaon) | 10 km |
| Hinjewadi Rajiv Gandhi IT Park | 15 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in SAIPLAZA?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026