Samruddhi Enclave

Pune · Shree Venkatesh Promoter & Builders

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100003179

Delivery and registration

When is the project declared for completion?

Samruddhi Enclave is registered with MahaRERA as P52100003179 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100003179
Registered on04 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Samruddhi Enclave record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shree Venkatesh Promoter is the promoter of record on 161 projects registered with MahaRERA, 27 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

161projects

registered with MahaRERA

27flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Samruddhi Enclave in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
A Wing1G+4-
B Wing1G+4-
C Wing1G+4-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Samruddhi Enclave, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000008560417/10/2021Anil Ambadas Karanjule vs Santosh Maruti Shelarorder passed

Location, Land & Connectivity

Located at Daund, Pune, 412203. Per the filed land record, the plot is bounded to the north by Gat No 199 P, to the south by Gat No 199 P, to the east by Gat No 219 and to the west by Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~47 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kharadi / EON IT Park47 km
Magarpatta / Hadapsar IT48 km
Pune Int'l Airport (Lohegaon)49 km
Pune Junction / city centre53 km
Baner–Balewadi belt64 km
Hinjewadi Rajiv Gandhi IT Park68 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boripardhi

Lonkar Residency
possession by Dec 2026 · Rohini Rajendra Lonkar
SKY County
possession by Dec 2027 · Deshmukh Developments
SAI Ananta
possession by Dec 2031 · Shree Venkateshwara Group
Nine Jewels Hill View
declared completion Dec 2025 · Milind Gulabrao Vatare
Sweet Home Pmay
Not filing quarterly progress reports · declared completion May 2025 · Deshmukh Developments
Tarangana Garden
Past its declared completion date · declared completion Mar 2023 · Tushar Dattatraya Gaikwad

Other RERA-registered projects in Pune

Samruddhi Heights
possession by Mar 2028 · Samruddhi Developers
Samruddhi Indraprasth Residency
possession by May 2029 · Samruddhi Group Landmark
Samruddhi Nabhangan
declared completion Jul 2018 · Samruddhi Reality
Samruddhi Nilaya
possession by Dec 2027 · Samruddhi Shelters
Samruddhi Park
declared completion Dec 2024 · B. K. Developers
Samruddhi Plaza
declared completion Sep 2023 · Trimurti Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.