Plotted Development Intelligence · Pune

TARANGANA GARDEN

P52100024327 · KEDGAON STATION DAUND · promoter Tushar Dattatraya Gaikwad

Certificate SignedDue 30 Mar 2023

Delivery & Registration

MahaRERA registrationP52100024327
Registered on05 Feb 2020
Promoter-declared completion30 Mar 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Tushar Dattatraya Gaikwad is the promoter of record on 36 projects, of which 8 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at KEDGAON STATION DAUND , S N 174 KEDGAON STATION TAL DAUND DIST PUNE , Haveli, Pune, 412203. Per the filed land record, the plot is bounded to the north by NANASAHEB GAIKWAD S N 174 PART, to the south by SHANKAR RAMBHAU BAROKAR SN 174 PART, to the east by 9 METER ROAD KEDGAON STATION ROAD and to the west by KASABAI TENGLE S N 174 PART. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~159 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)158 km
Kharadi / EON IT Park159 km
Magarpatta / Hadapsar IT162 km
Pune Junction / city centre166 km
Baner–Balewadi belt172 km
Hinjewadi Rajiv Gandhi IT Park174 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boripardhi

Lonkar Residency
possession by Dec 2026 · Rohini Rajendra Lonkar
SKY County
possession by Dec 2027 · Deshmukh Developments
SAI Ananta
possession by Dec 2031 · Shree Venkateshwara Group
Nine Jewels Hill View
declared completion Dec 2025 · Milind Gulabrao Vatare
Sweet Home Pmay
Not filing quarterly progress reports · declared completion May 2025 · Deshmukh Developments
Chaitanya Srusti
declared completion Dec 2024 · Chaitanya Developers

Other RERA-registered projects in Pune

Tarangana Nakshatra
declared completion Dec 2018 · Tarangana Nakshatra
Tarangana Square
declared completion Jun 2024 · Tarangana Square
Taras Heights
possession by Oct 2026 · Taras Landmark
Tathastu
declared completion Dec 2018 · Balasai Associates
Tathastu
possession by Dec 2030 · SAI Asha Infra-Edge City
Tathastu Homes
declared completion Jun 2026 · Shri Bhagyalaxmi Infracon

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026