Shalimar Residency

Sathe Vasti · Shalimar Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100008184

Delivery and registration

When is the project declared for completion?

Shalimar Residency is registered with MahaRERA as P52100008184 and the promoter has declared completion for 30 Sep 2019.

30 Sep 2019

declared completion

84months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100008184
Registered on18 Aug 2017
Promoter-declared completion30 Sep 2019
Current statusCertificate Signed
Against todayabout 84 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shalimar Residency record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shalimar Constructions is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shalimar Residency in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Shalimar Residency1G+530 Sep 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2019Respected Sir/Madam, We Shalimar Constructions have registered the project under MAHARERA by the name “SHALIMAR RESIDENCY”. And the project registration number is P52100008184.

Location, Land & Connectivity

Located at Sathe Vasti, Dhanori - Lohegaon Road, Pune City, Pune, 411047. Per the filed land record, the plot is bounded to the north by Adjoined sr no 280 part, to the south by Asjoined sr no 280 part, to the east by Adjoined st no 280part and to the west by 9 mt wide internal road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)2 km
Kharadi / EON IT Park6 km
Pune Junction / city centre9 km
Magarpatta / Hadapsar IT9 km
Baner–Balewadi belt15 km
Hinjewadi Rajiv Gandhi IT Park19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Lohegaon

Aayush Exotica
possession by Sep 2026 · Aayush Properties
Chandan Heritage
possession by Sep 2026 · City Developers
Youthika
possession by Oct 2026 · Krushnarang Group
Pankaj Aasmaan Phase V
possession by Dec 2026 · Pankaj Developers
Aayush Wisteria
possession by Dec 2026 · Pritam Kantilal Khandve
Divine Garden Phase 1
possession by Dec 2026 · Shriram Associates

Major developers building in Lohegaon

Other RERA-registered projects in Pune

Shalini
possession by May 2028 · K2gnn Homes LLP
Shalom Harmony
possession by Mar 2028 · Chrishh Holdings
Shambhavi
declared completion Oct 2023 · M/S Kharde Patil
Shambhavi Classic
declared completion Jun 2018 · N K Company
Shambhavi Gold
possession by Dec 2027 · N K Company
Shambhavi Palace
declared completion May 2023 · N K Company

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026