MahaRERA Property Intelligence · Pune

Shikrapur Trade Center Phase III

P52100048886 · Shikrapur · promoter Pride Landmarks

Certificate SignedDue 31 Mar 2026

Delivery & Registration

MahaRERA registrationP52100048886
Registered on24 Jan 2023
Promoter-declared completion31 Mar 2026
Current statusCertificate Signed
Against todayabout 4 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~100.0% of the estimated project cost incurred as of the last certificate (₹2.60 Cr spent against a ₹2.60 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
Shikrapur Trade Center Phase III1G+3-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Shikrapur, Shikrapur Village, Shirur, Pune, 412208. Per the filed land record, the plot is bounded to the north by Gut No 16 4, to the south by Gut No 16 2, to the east by 9 mtr wide road and to the west by Gut no 16 14. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre2 km
Magarpatta / Hadapsar IT5 km
Kharadi / EON IT Park6 km
Pune Int'l Airport (Lohegaon)6 km
Baner–Balewadi belt12 km
Hinjewadi Rajiv Gandhi IT Park17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pride Landmarks is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Pride Landmarks

Other RERA-registered projects in Shikrapur

Adinath Shrushti
possession by Aug 2026 · Adinath Realty
Sharanya Galaxy
possession by Dec 2026 · Sharanya Constructions
Harmony
possession by Dec 2026 · Nandakumar Lapalikar
Abhilasha Wing A AND Wing B
possession by Dec 2026 · M/S Kudale Sable Builders
Maitri Gold
possession by Dec 2026 · Maitri Developers AND Builders
Patil Plaza
Not filing quarterly progress reports · possession by Dec 2026 · Devidas Patil

Major developers building in Shikrapur

Other RERA-registered projects in Pune

Shikrapur Trade Centre Phase I
declared completion Sep 2025 · Pride Landmarks
Shikrapur Trade Centre Phase II
declared completion Sep 2025 · Pride Landmarks
Shikshak Co-Operative Housing Society Ltd
possession by Dec 2028 · Deshpande Realty
Shillim Residences - Phase 1
declared completion Dec 2019 · Writer Lifestyle Pvt. Ltd.
Shiloh
declared completion Dec 2018 · Viraj Properties
Shilp Shantivan
possession by Jun 2028 · Echo Stone Buildcon

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026