MahaRERA Property Intelligence · Pune

Shiv Sparsh Phase II

P52100023602 · Dhayari · promoter Sumangal Projects

Certificate SignedDue 31 Jul 2024

Delivery & Registration

MahaRERA registrationP52100023602
Registered on20 Dec 2019
Promoter-declared completion31 Jul 2024
Current statusCertificate Signed
Against todayabout 24 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sumangal Projects is the promoter of record on 7 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+0.

BuildingWingsFloorsDeclared completion
C2 And C3 5Th Floor1G+0-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 4 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202131 Jul 2023The promotor has completed the project-Shiv Sparsh Phase-II 100%. However, fire NOC and lift NOC is awaited. Therefore the promotor can not apply for obtaining Completion certifica
30 Jun 202130 Jun 2022The promoter could not complete the remaining part of the project i.e. approximately 20% due to difficulties faced during lockdown period imposed by the local authority/government
30 Jun 202131 Jul 2024The promoter has completed the project- Shiv Sparsh phase-II 100% . However Fire NOC and lift NOC ios awaited, therefore the promoter cannot apply for obtaining completion certific
30 Jun 202131 Jan 2024The promoter has completed the project Shiv Sparsh PhaseII 100%. However, Fire NOC and Lift NOC is awaited, therefore the promoter cannot apply for obtaining completion certificate

Location, Land & Connectivity

Located at Dhayari, Benkar Vasti, Haveli, Pune, 411041. Per the filed land record, the plot is bounded to the north by S No 08 Part, to the south by S No 08-20 and 08-21, to the east by Brook and to the west by Wing C1. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~46 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Baner–Balewadi belt46 km
Hinjewadi Rajiv Gandhi IT Park46 km
Pune Junction / city centre51 km
Magarpatta / Hadapsar IT55 km
Kharadi / EON IT Park58 km
Pune Int'l Airport (Lohegaon)59 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhayari

Aqura Pride
possession by Sep 2026 · Aqura Builder And Developer Private Limi
Majestique Swapnangan Wing A And Wing B
possession by Sep 2026 · Majestique Horizon LLP
Tridal Samruddhi
possession by Sep 2026 · M/s. Tridal Associates
Vasant Vihar A Wing
possession by Sep 2026 · A R Developers
Homedale
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Homedale Phase 2
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop

Major developers building in Dhayari

Other RERA-registered projects in Pune

Shiv Srushti
possession by Dec 2026 · Chaitanya Buildcon
Shiv Tirth
declared completion Dec 2021 · Chaitanya Buildcon
Shiv Vihar
declared completion Dec 2021 · Royal Construction
Shiv ZEN World - Phase I
declared completion Dec 2021 · Shubh Housing
Shiv Zen World Phase II
declared completion Dec 2023 · Shubh Housing
Shiv ZEN World Phase III
declared completion Aug 2025 · Shubh Housing

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026