Shiv Sparsh Phase II

Dhayari · Sumangal Projects

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100023602

Delivery and registration

When is the project declared for completion?

Shiv Sparsh Phase II is registered with MahaRERA as P52100023602 and the promoter has declared completion for 31 Jul 2024.

31 Jul 2024

declared completion

26months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100023602
Registered on20 Dec 2019
Promoter-declared completion31 Jul 2024
Current statusCertificate Signed
Against todayabout 26 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shiv Sparsh Phase II record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sumangal Projects is the promoter of record on 8 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shiv Sparsh Phase II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+0.

BuildingWingsFloorsDeclared completion
C2 And C3 5Th Floor1G+0-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022The promoter could not complete the remaining part of the project i.e. approximately 20% due to difficulties faced during lockdown period imposed by the local authority/government
30 Jun 202231 Jul 2023The promotor has completed the project-Shiv Sparsh Phase-II 100%. However, fire NOC and lift NOC is awaited. Therefore the promotor can not apply for obtaining Completion certifica
31 Jul 202331 Jan 2024The promoter has completed the project Shiv Sparsh PhaseII 100%. However, Fire NOC and Lift NOC is awaited, therefore the promoter cannot apply for obtaining completion certificate
31 Jan 202431 Jul 2024The promoter has completed the project- Shiv Sparsh phase-II 100% . However Fire NOC and lift NOC ios awaited, therefore the promoter cannot apply for obtaining completion certific

Location, Land & Connectivity

Located at Dhayari, Benkar Vasti, Haveli, Pune, 411041. Per the filed land record, the plot is bounded to the north by S No 08 Part, to the south by S No 08-20 and 08-21, to the east by Brook and to the west by Wing C1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~46 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Baner–Balewadi belt46 km
Hinjewadi Rajiv Gandhi IT Park46 km
Pune Junction / city centre51 km
Magarpatta / Hadapsar IT55 km
Kharadi / EON IT Park58 km
Pune Int'l Airport (Lohegaon)59 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhayari

Aqura Pride
possession by Sep 2026 · Aqura Builder And Developer Private Limi
Majestique Swapnangan Wing A And Wing B
possession by Sep 2026 · Majestique Horizon LLP
Tridal Samruddhi
possession by Sep 2026 · M/s. Tridal Associates
Vasant Vihar A Wing
possession by Sep 2026 · A R Developers
Homedale
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Navjyot Abha Phase II B And D
Not filing quarterly progress reports · possession by Dec 2026 · Sumeru Buildcon Private Limited

Major developers building in Dhayari

Other RERA-registered projects in Pune

Shiv Srushti
possession by Mar 2028 · M/s Om Ganesh Developers
Shivaay Landmark
declared completion Dec 2025 · Shivaay Reality
Shivai Sahakari Gruh Nirman Sanstha Maryadit
possession by Dec 2026 · Mayuresh Developers
Shivalay 21
possession by Dec 2027 · Shree Gurudatta Developers
Shivalay Residency
possession by Mar 2027 · Not Available
Shivali & Neelratan Apartment Condominium
possession by Dec 2028 · D&T Properties Unit-5

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026