MahaRERA Property Intelligence · Pune

Shree Aangan

P52100003275 · Dighi · promoter Shree Infrastructure

Certificate SignedDue 28 Feb 2022

Delivery & Registration

MahaRERA registrationP52100003275
Registered on05 Aug 2017
Promoter-declared completion28 Feb 2022
Current statusCertificate Signed
Against todayabout 53 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Phase - I Shree Aangan1G+530 Jun 2019
Phase - II Shree Aangan1-30 Jun 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
28 Feb 202229 Jun 2020At the time of registration we had given expected date of project completion as 30th June 2019. However we are not able to obtain completion certificate till the due date due to so
28 Feb 202229 Apr 2021Need Extention
28 Feb 202230 Aug 2021Due to the pandemic (Covid 19 ) situation, we are unable to get a completion certificate before due date. So require more extension..

Location, Land & Connectivity

Located at Dighi, Alandi Road, Haveli, Pune, 411015. Per the filed land record, the plot is bounded to the north by 6 Meter Wide Road, to the south by Part of Sr No 20, to the east by Part of Sr No 20 and to the west by 6 Meter Wide Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)6 km
Pune Junction / city centre9 km
Kharadi / EON IT Park10 km
Baner–Balewadi belt12 km
Magarpatta / Hadapsar IT12 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dhanori

Gada Elina
possession by Jul 2026 · Kubix Realties LLP
Belmont Aster
possession by Aug 2026 · Prakash Ganpatrao Kshirsagar
Belmont Jasmine
possession by Aug 2026 · Uttam Nivrutti Dimbale
Murli Manohar Heights
possession by Sep 2026 · Padmanabh Associates
Yash Grecia- E Wing
possession by Sep 2026 · Akshay Enterprises
Aaiji Crystal Phase I
possession by Oct 2026 · Aaiji Developers

Major developers building in Dhanori

Other RERA-registered projects in Pune

Shree Aarti
possession by Aug 2027 · M.s.naik & Co
Shree Apartment
declared completion Sep 2022 · Revive Homes LLP
Shree Apartment
declared completion Dec 2025 · S R Developers
Shree Apartment Phase 2
declared completion Dec 2019 · Nandini Mangaldeep Vishnu Associates
Shree Apartment Phase1
declared completion Dec 2019 · Nandini Mangaldeep Vishnu Associates
Shree Arambh
declared completion Dec 2024 · Sangram Deepak Chavan

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026