MahaRERA Property Intelligence · Pune

SHREE ASHTVINAYAK PARK

P52100017473 · Pimpri Chinchawad · promoter Mohit Developers

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52100017473
Registered on13 Aug 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Mohit Developers is the promoter of record on 31 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Shree Ashtvinayak Park1G+531 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Pimpri Chinchawad, Pimprigaon road, Pune City, Pune, 411017. Per the filed land record, the plot is bounded to the north by Sonigara garden society, to the south by Proposed 9m road, to the east by Property of Tanaji Nadhe and to the west by Property of Kashinath Nadhe. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~80 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kharadi / EON IT Park80 km
Magarpatta / Hadapsar IT81 km
Pune Int'l Airport (Lohegaon)83 km
Pune Junction / city centre86 km
Baner–Balewadi belt97 km
Hinjewadi Rajiv Gandhi IT Park102 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Rahatani

Adi Amma Insperia
possession by Jul 2026 · J N Realty And Homes
Devkamal Heights
possession by Oct 2026 · MRS Kamal Devram Hole
KK Mangalam Emerald
possession by Oct 2026 · Shah Associates & Properties
AUM Vertex
possession by Dec 2026 · Aum Buildcon
KK Capitol
possession by Dec 2026 · Shah AND Associates
Tamara
possession by Dec 2026 · Goldfinger Kataria Urban Developments

Major developers building in Rahatani

Other RERA-registered projects in Pune

Shree Balaji Heights
declared completion Jun 2026 · Shree Balaji Developers
Shree Bhavani Height
declared completion Feb 2022 · Shree Bhavani Developers
Shree Business Icon
possession by Dec 2026 · Shree Enterprises
Shree Chinar Cooperative Society Limited
declared completion Mar 2026 · Saachee Infra
Shree Chintamani Apartments
declared completion Sep 2022 · Nishikant Sharad Chaudhari
Shree Chsl
possession by Dec 2028 · Kotibhaskar Infrastructures &develop

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026