MahaRERA · the public record
Tamara
Pimpale Saudhagar · Goldfinger Kataria Urban Developments
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Dec 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100013230
Delivery and registration
When is the project declared for completion?
Tamara is registered with MahaRERA as P52100013230 and the promoter has declared completion for 30 Dec 2026.
30 Dec 2026
declared completion
3months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100013230 |
| Registered on | 21 Sep 2017 |
| Promoter-declared completion | 30 Dec 2026 |
| Current status | Certificate Signed |
| Against today | 3 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Tamara record 34 quarterly progress reports since registration.
34quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 34 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Goldfinger Kataria Urban is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
2projects
registered with MahaRERA
0flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In Tamara, ₹54.70 Cr of a declared ₹108.63 Cr estimated project cost is reported as incurred, about 50.4%, as at the last certified filing with MahaRERA.
50.4%
₹54.70 Cr
of ₹108.63 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Tamara, 230 of 341 homes filed with MahaRERA are recorded as sold or booked, about 67%, and 111 remain available.
67%sold
230 of 341 homes
₹181.06 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹134.80 Cr (about 74%) is recorded as collected and ₹49.51 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 230 registered agreements, the effective carpet rate is ₹9,506/sqft, with eight in ten falling between ₹7,067 and ₹11,553 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 13 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 241 homes carry one, and 155 of the 396 are recorded unsold. Since we started watching this ledger, 6 homes have moved out of the unsold list, most recently on 04 September 2026.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 207 | 701 sqft | Rs 55.43 lakh typical, over Rs 43.95 lakh to Rs 68.64 lakh | 51 filed at this size |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
In Tamara, 127 of the 155 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15 and 341 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| A building | 1 | G+14 | 43 | 30 Dec 2026 |
| B Building | 1 | G+15 | 43 | 30 Dec 2026 |
| C Building | 1 | G+15 | 43 | 30 Dec 2026 |
| D - uprise | 1 | G+15 | 102 | 30 Dec 2026 |
| E - uprise | 1 | G+8 | 110 | 30 Dec 2026 |
Unit mix on the filing: 312 residential and 29 non-residential (shops/offices).
Legal and disputes
What disputes are disclosed?
1 complaint is on the MahaRERA record for Tamara, with orders passed in 1 of them.
1complaint
1with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC12504065 | 18/11/2025 | Sujit Shankar Bhosale vs Goldfinger Kataria Urban Developments | order passed |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Dec 2020 | "It was pleasure to complete the project 5 months before the date of completing the project announced in RERA. The date of completing the Project was given as 31.12.17 & we have re |
| 31 Dec 2020 | 30 Dec 2026 | Due to Covid 19 and Revise sanction as per new UDCPR Rule. |
Location, Land & Connectivity
Located at Pimpale Saudhagar, Pimple Saudhagar, Haveli, Pune, 411017. Per the filed land record, the plot is bounded to the north by Property owned by Kokane and Nakate, to the south by 18 M wide road, to the east by Kashitish Co operative Hsg Society and to the west by Rose e meher society. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 5 km |
| Baner–Balewadi belt | 5 km |
| Pune Junction / city centre | 13 km |
| Pune Int'l Airport (Lohegaon) | 14 km |
| Kharadi / EON IT Park | 17 km |
| Magarpatta / Hadapsar IT | 18 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.