MahaRERA Property Intelligence · Pune

SHREE SWAMI SAMARTH COMPLEX

P52100011468 · promoter Ramesh Construction And

Certificate SignedDue 28 Feb 2021

Delivery & Registration

MahaRERA registrationP52100011468
Registered on31 Aug 2017
Promoter-declared completion28 Feb 2021
Current statusCertificate Signed
Against todayabout 65 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ramesh Construction And is the promoter of record on 163 projects, of which 25 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
SHREE SWAMI SAMARTH COMPLEX1G+331 Aug 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
28 Feb 202130 Aug 2020We are the promoters of abovementioned housing Project located at Gat No.449, at Donaje, Tal. Haveli, Dist. Pune-411025. The said proejct is consisting of one building. Due to wat

Location, Land & Connectivity

Located at Haveli, Pune, 411025. Per the filed land record, the plot is bounded to the north by GAT NO 448, to the south by GAT NO 450, to the east by GAOTHAN ROAD and to the west by GAOTHAN. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~84 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park84 km
Baner–Balewadi belt89 km
Pune Junction / city centre99 km
Pune Int'l Airport (Lohegaon)100 km
Kharadi / EON IT Park104 km
Magarpatta / Hadapsar IT105 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Gorhe Bk

OM Tapovan
possession by Dec 2026 · OM Tapovan
Panna Niwas
possession by Dec 2026 · Unique Developers
Vrundavan
possession by Jun 2027 · SAI Ganesh Associates
Mindspace Villas Phase I
possession by Dec 2028 · MS Lifestyle Resorts
Pakhar 2 AND 3 BHK Nests
possession by Dec 2028 · Royal Developers AND Builders
The Back Water Residency Phase II - B Building
Deregistered by MahaRERA · declared completion Dec 2025 · LNK Projects Through Proprietor Mr Naray

Other RERA-registered projects in Pune

Shree Swami Samarth Residency
declared completion Mar 2024 · Anil Vasantrao Chavan
Shree Swami Samarth Residency
possession by Mar 2027 · Nitin Tukaram Padwal
Shree Swarajya Park
possession by Dec 2027 · Shreegruha Nirman Infra Projects LLP
Shree Swarup
declared completion Jun 2019 · A & A Associates
Shree Tejomay
possession by Dec 2027 · Mankar Joshi Developers LLP
Shree Venkatesh SAI Residency
possession by Mar 2027 · Shree Venkatesh SAI Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026