30 Jun 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100008103

Delivery and registration

When is the project declared for completion?

SHREE SWARUP is registered with MahaRERA as P52100008103 and the promoter has declared completion for 30 Jun 2019.

30 Jun 2019

declared completion

87months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100008103
Registered on18 Aug 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 87 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE SWARUP record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE SWARUP in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
SHREE SWARUP1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2019Material Unavailability and Shortage.

Location, Land & Connectivity

Located at Pune City, Pune, 411009. Per the filed land record, the plot is bounded to the north by Ajd S No 173 P, to the south by Wide Road, to the east by Ajd S No 173 P and to the west by Wide Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~181 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Junction / city centre181 km
Baner–Balewadi belt181 km
Magarpatta / Hadapsar IT181 km
Hinjewadi Rajiv Gandhi IT Park183 km
Kharadi / EON IT Park185 km
Pune Int'l Airport (Lohegaon)188 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every A & A Associates project & its RERA track record →

Other RERA-registered projects in Parvati

Serenity Residency
possession by Sep 2026 · Buttepatil Properties
Trimurti
possession by Sep 2026 · Datar Engineering AND Consultancy Privat
Vishwas Apartment
possession by Sep 2026 · Manomay Constructions
Arco Skylife
possession by Dec 2026 · Arco Engineers
Moreshwar Enclave
possession by Dec 2026 · Moreshwar Developers
Shantanu Height
possession by Dec 2026 · Shashidhar Singh

Other RERA-registered projects in Pune

Shree Tejomay
possession by Dec 2027 · Mankar Joshi Developers LLP
Shree Venkatesh SAI Residency
possession by Mar 2027 · Shree Venkatesh SAI Associates
Shree Vihar
declared completion Jan 2021 · Shree Developers
Shree Vishnunarayan Complex
declared completion Dec 2017 · Mahesh Ramchandra Tikhe
Shree Vishwa
declared completion Jan 2022 · Shree Developers
Shree Vithal Plaza
declared completion Jun 2019 · Krishna Mahaling Kharade

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.