Pune/Project record

MahaRERA · the public record

SHREE VISHWA

LONI KALBHOR · SHREE DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jan 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jan 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100004359

Delivery and registration

When is the project declared for completion?

SHREE VISHWA is registered with MahaRERA as P52100004359 and the promoter has declared completion for 31 Jan 2022.

31 Jan 2022

declared completion

56months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100004359
Registered on09 Aug 2017
Promoter-declared completion31 Jan 2022
Current statusCertificate Signed
Against todayabout 56 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE VISHWA record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE VISHWA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SHREE VISHWA1G+431 Jul 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2021AS PER FORM E

Location, Land & Connectivity

Located at LONI KALBHOR, LOANI KALHBOR, Haveli, Pune, 412201. Per the filed land record, the plot is bounded to the north by GAT NO 17, to the south by GAT NO 14, to the east by 9 METER ROAD and to the west by GAT NO 15. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~67 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park67 km
Baner–Balewadi belt71 km
Pune Junction / city centre80 km
Magarpatta / Hadapsar IT85 km
Pune Int'l Airport (Lohegaon)86 km
Kharadi / EON IT Park87 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Developers is the promoter on 44 MahaRERA-registered projects, of which 7 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shree Developers project & its RERA track record →

Other flagged projects by Shree Developers

Shree Developers
Past its declared completion datePune
Shree Developers
Deregistered by MahaRERAPune
Shree Developers
Past its declared completion datePune
Shree Developers
Past its declared completion datePune

Other RERA-registered projects in Loni Kalbhor

Arvan Residency
possession by Dec 2026 · Sanskruti Developers
Keshavyog Residency
possession by Dec 2026 · Siddhivinayak Builders
Muktai Park Phase II
possession by Dec 2026 · Shivshakti Buildcon
Platinum Nirvana
possession by Dec 2026 · Platinum Developers
Swami Homes
possession by Jan 2027 · S S Developers
Krishnai Residency
possession by Mar 2027 · Ivana Properties

Other RERA-registered projects in Pune

Shree Vithal Plaza
declared completion Jun 2019 · Krishna Mahaling Kharade
Shree Vitthal Venue
declared completion Sep 2024 · Miracle Developers
Shree Yash Bhavani Developers
declared completion Dec 2023 · Shree Yash Bhavani Developers
Shreeansh Avenue
declared completion Dec 2022 · Balasaheb Narayan Bhangire
Shreedattanagar
declared completion Dec 2024 · Shlok Enterprises
Shreedhar Nilay
possession by Dec 2028 · Opulent Landmarks

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026