MahaRERA Property Intelligence · Pune

SIDDHI PLAZA

P52100015648 · GANESH PETH · promoter Shree Developers

Certificate SignedDue 31 Dec 2021

Delivery & Registration

MahaRERA registrationP52100015648
Registered on15 Mar 2018
Promoter-declared completion31 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
SIDDHI PLAZA1G+730 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202131 Dec 2021The reason for delayed for Non-completion is that there was some disputes between one commercial tenant and residential tenants, and other financial obligation and thereafter COVID

Location, Land & Connectivity

Located at GANESH PETH, NA, Pune City, Pune, 411002. Per the filed land record, the plot is bounded to the north by PMC ROAD, to the south by PMC ROAD, to the east by CTS NO 592 GANESH PETH and to the west by CST NO 595 GANESH PETH. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre2 km
Magarpatta / Hadapsar IT7 km
Kharadi / EON IT Park9 km
Pune Int'l Airport (Lohegaon)9 km
Baner–Balewadi belt10 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Developers is the promoter on 44 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shree Developers project & its RERA track record →

Other flagged projects by Shree Developers

Shree Developers
Past its declared completion datePune
Shree Developers
Deregistered by MahaRERAPune
Shree Developers
Past its declared completion datePune

Other RERA-registered projects in Shukrawar Peth

Naik Heritage
possession by Aug 2026 · Jamaluddin Khan
Niwant
possession by Sep 2026 · Gokhale Ventures LLP
Kawal Arcade
possession by Sep 2026 · Sethi Greenscape Venture
Samasta Barajati Gujarathi Mahajan
possession by Sep 2026 · Shri Samasta Barajatis Gujrati Mahajan
Dhanlaxmi Market
possession by Dec 2026 · Dhanlaxmi Infra
Aakankssha Sanskruti
possession by Dec 2026 · Aakankssha Developer

Major developers building in Shukrawar Peth

Other RERA-registered projects in Pune

Siddhi Plaza
possession by Dec 2026 · Shree Developers
Siddhi Samruddhi
declared completion Nov 2021 · Sanghvi Developers
Siddhi Sankul
possession by Sep 2026 · Jitendra Constructions AOP
Siddhi -Siddhachal
possession by Aug 2026 · Bhairav Promoters Unit Number 1
Siddhi Skylark
declared completion Sep 2025 · Gangadhar Ramesh Bhalekar
Siddhi Towers A Wing
declared completion Jan 2023 · Satish Baswant Patil

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026