Certificate SignedDue 31 Dec 2023

Delivery & Registration

MahaRERA registrationP52100032823
Registered on02 Feb 2022
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shri Bhushan Developers is the promoter of record on 26 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
SHRI SANKUL1G+131 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at OPP. CREATIVE ACADEMY, BEHIND T.C. COLLEGE, PRAGATI NAGAR, BARAMATI, NEAR TANDULWADI ROAD, Baramati, Pune, 413102. Per the filed land record, the plot is bounded to the north by GAT NO 171-2-2, to the south by GAT NO 171-2-3 AND ROAD, to the east by GAT NO 171-2-3 and to the west by GAT NO 171-2-1. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shri Bhushan Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shri Bhushan Developers

Shri Bhushan Developers
FlaggedPune

Other RERA-registered projects in Baramati

Nirvana Elite
possession by Jul 2026 · Akash Jayesh Associates
Sharada Baug
possession by Aug 2026 · Mandar Shrikant Sikachi
G G Capital
possession by Aug 2026 · GG Builders AND Developers
Mayureshwar Icon
possession by Sep 2026 · Mayureshwar Reality AND Developers
Gadhavenanaware Heights
possession by Sep 2026 · Shri Developers
Shivshri Heights
possession by Sep 2026 · Shivashri Buildcon

Major developers building in Baramati

Other RERA-registered projects in Pune

Shri Shikharji Darshan Apts
declared completion Mar 2025 · Rajnesh Shrikumar Mehta
Shri Sukhshanti
declared completion Dec 2019 · Gokhale Homes LLP
Shri Swami Residency
declared completion Jan 2024 · Shri Construction And Developers
Shri Swami Samarth Complex
declared completion Jun 2026 · Siddhivinayak Builders AND Developers
Shri Swami Samarth Residency
declared completion Mar 2026 · M/S Shri Swami Samarth Builders AND Deve
Shri Swami Samrth Recedncy
declared completion Aug 2018 · BSK Developers AND Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.