Pune/Project record

MahaRERA · the public record

Shruti Icon

Pune · Warke Developers Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100011149

Delivery and registration

When is the project declared for completion?

Shruti Icon is registered with MahaRERA as P52100011149 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100011149
Registered on31 Aug 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shruti Icon record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 28 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Warke Developers is the promoter of record on 3 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shruti Icon in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
A Wing1G+731 Aug 2018
B Wing1G+731 Aug 2018
C Wing1G+731 Aug 2018
D Wing1G+731 Aug 2018

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for Shruti Icon, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000002201010/09/2018Archana Singh vs Nilesh Pandharinath patilorder passed
CC00500000005400705/02/2020Archana Singh vs Nilesh Patilorder passed
CC00500000026938214/09/2023Gangadhar Bapurao Gunjite vs WARKE DEVELOPERS PRIVATE LIMITEDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 20231. We were applied for RERA Registration under MahaRERA in the Pune Region and it was difficult during initial stage of project registration under MAHARERA to judge all the pros an

Location, Land & Connectivity

Located at Haveli, Pune, 411044. Per the filed land record, the plot is bounded to the north by Gat No 706 Old Gat No 1070, to the south by 18 m Road, to the east by Remaining Part of Gat No 705 Old Gat no1069 and to the west by Gat No 751 Old Gat No 1114. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park9 km
Baner–Balewadi belt12 km
Pune Int'l Airport (Lohegaon)19 km
Pune Junction / city centre19 km
Kharadi / EON IT Park22 km
Magarpatta / Hadapsar IT24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nigdi Pradhikaran

THE Saga
possession by Sep 2026 · Nest Saswad Realty LLP
Aashirwad Homes
possession by Dec 2026 · Nest Saswad Realty LLP
Paradise Residency
possession by Dec 2026 · Balaji Developers
Shuban Enclave
possession by Dec 2026 · Sahyadri Devcon
Vision Vanessa
possession by Dec 2026 · P4 Group
Swastik Vyom
possession by Mar 2027 · Swastik Venture

Other RERA-registered projects in Pune

Shruti Icon E Wing
declared completion Mar 2025 · Maitri Combines
Shruti Prestige A Wing
declared completion Dec 2019 · Shruti Developers
Shruti Pushp
declared completion Feb 2019 · Shruti Constructions
Shruti Pushp
declared completion Dec 2022 · Prasiddhi Constructions
Shuban Enclave
possession by Dec 2026 · Sahyadri Devcon
Shubh Aangan
declared completion Jun 2023 · Creative Properties

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026