SIDDHIVINAYAK AURA

P52100032229 · TALEGAON DABHADE · promoter Ganesh Mohanrao Kakade

Certificate SignedDue 31 Dec 2023

Delivery & Registration

MahaRERA registrationP52100032229
Registered on15 Dec 2021
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ganesh Mohanrao Kakade is the promoter of record on 13 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
C WING1G+431 Dec 2023
D WING1G+431 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
District Judge Pune120/20202020Rca Order Passed In Favour Of Promotor

Location, Land & Connectivity

Located at TALEGAON DABHADE, TALEGAON CHAKAN ROAD, Mawal, Pune, 410507. Per the filed land record, the plot is bounded to the north by COLONY ROAD 12 MW, to the south by OPEN SPACE, to the east by COLONY ROAD 12 MW and to the west by S NO 10 CHA 2 DWARAKA CO OP HSG SOC. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ganesh Mohanrao Kakade is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Ganesh Mohanrao Kakade

Ganesh Mohanrao Kakade
FlaggedPune
Ganesh Mohanrao Kakade
FlaggedPune

Other RERA-registered projects in Talegaon Dabhade

Real Dream Homes Wing C AND D
possession by Jul 2026 · Real Buildcon Builders AND Developers
ECO City
possession by Aug 2026 · Namrata Promoters AND Builders
Luxuria
possession by Aug 2026 · Prammukh Associates
Arunoday Classic A Wing
possession by Sep 2026 · Kedar Harishchandra Khandge
Hillcrest
possession by Oct 2026 · Swapnashilp Buildcon
Greendale ENA
possession by Dec 2026 · M/s. Karpe Construction Company

Major developers building in Talegaon Dabhade

Other RERA-registered projects in Pune

Siddhivinayak Dream Homes
declared completion Dec 2020 · Ravindra Yamnaji Bhor
Siddhivinayak Dream Homes C,D Wing
declared completion Apr 2026 · Ravindra Yamnaji Bhor
Siddhivinayak Gruhprakalp
declared completion Dec 2020 · Vaishnav Group Builders AND Developers
Siddhivinayak Height
declared completion Dec 2025 · Laxmi Developers
Siddhivinayak Nest
declared completion Dec 2022 · Ganesh Mohanrao Kakade
Siddhivinayak Park
declared completion Dec 2024 · Siddhivinayak Construction AND Developer

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026