Signature Tower II

Shivajinagar · Summit Property Ventures LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100021118

Delivery and registration

When is the project declared for completion?

Signature Tower II is registered with MahaRERA as P52100021118 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100021118
Registered on31 May 2019
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Signature Tower II record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Summit Property Ventures is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Signature Tower II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
Signature Tower II1G+1130 Sep 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2023Due to Non availability of labour and construction raw materials such as cement and sand, Due to torrential monsoon rainfall, the water was accumulated on the project site resultin

Location, Land & Connectivity

Located at Shivajinagar, Model Colony, Pune City, Pune, 411016. Per the filed land record, the plot is bounded to the north by Bank of Baroda Society, to the south by Iris Garden Society, to the east by Road and Anand Ashram Society and to the west by Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre4 km
Baner–Balewadi belt7 km
Magarpatta / Hadapsar IT10 km
Pune Int'l Airport (Lohegaon)11 km
Kharadi / EON IT Park11 km
Hinjewadi Rajiv Gandhi IT Park12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shivajinagar

Vallabh Co-Op Housing Society
possession by Sep 2026 · Srkd Landmark LLP
16 Lakaki
possession by Dec 2026 · Shah Kulkarni Associates LLP
Eshaan
possession by Dec 2026 · Naman Realty
Garud House Apartment Condominium
possession by Dec 2026 · Fortune Developers
Mountain View CO-Oprative Housing Society
possession by Dec 2026 · D & T Properties
Neev
possession by Dec 2026 · J Square Projects LLP

Other RERA-registered projects in Pune

Signature Tower Phase 2
possession by Dec 2031 · Samarth Builders
Signature Villas
possession by Mar 2027 · Shirish Nihalchand Lodha
Signis
possession by Nov 2028 · BM Build Spaces LLP
Signix
declared completion Dec 2025 · Choulwar Associates
Signum
declared completion Nov 2023 · Pride Realty
Sikandar Apartments
declared completion Aug 2023 · Radhika Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.